4050 S MARCASEL AVE 90066

Certificate Information: 4050 S MARCASEL AVE 90066

Application / Permit
21010-30000-03626
Plan Check / Job No.
B21WL03216
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW ALQ AND ATTACHED STORAGE *** see comments ***
Permit Issued
Issued on 12/6/2022
Issuing Office
West Los Angeles
Current Status
Issued on 12/6/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/20/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 KAVIAN REFAHI
Corrections Issued 8/9/2021 KAVIAN REFAHI
Quality Review Completed 8/9/2021 CHIHARU SUZUKI
Applicant returned to address corrections 3/8/2022 KAVIAN REFAHI
Applicant returned to address corrections 3/10/2022 KAVIAN REFAHI
Applicant returned to address corrections 4/27/2022 KAVIAN REFAHI
Plan Check Approved 5/2/2022 KAVIAN REFAHI
Building Plans Picked Up 5/9/2022 APPLICANT
Issued 12/6/2022 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 12/16/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/16/2021 JOSE HERNANDEZ
Sewer availability Cleared 12/16/2021 JOSE HERNANDEZ
Hydrant and Access approval Cleared 3/7/2022 LARRY REDDEN
Low Impact Development Cleared 3/21/2022 TA ANH
Roof/Waste drainage to street Cleared 4/19/2022 STEVE MELGAR

Contact Information

Architect Hodgdon,, Emily Elizabeth; Lic. No.: C30043 1331 BERKELEY STREET # 4      SANTA MONICA, CA 90404
Contractor Sawyer Robert; Lic. No.: 817415-B 8116 GONZAGA AVENUE      LOS ANGELES, CA 90045
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/12/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 1/30/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 2/7/2023 Approved JESUS RODRIGUEZ
Reinforced Concrete Frame 2/17/2023 Corrections Issued HERBERT GIRON
Masonry Wall/Backfill 2/23/2023 Partial Approval HERBERT GIRON
Masonry Wall/Backfill 3/24/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 7/11/2023 Partial Approval JESUS RODRIGUEZ
Insulation 9/6/2023 Partial Approval JESUS RODRIGUEZ
Drywall Nailing 9/15/2023 Partial Approval JESUS RODRIGUEZ
Green Building Rough 9/15/2023 Not Ready for Inspection JESUS RODRIGUEZ
Drywall Nailing 10/26/2023 Partial Approval JESUS RODRIGUEZ
Green Building Rough 10/26/2023 Not Ready for Inspection JESUS RODRIGUEZ
Light Gage Steel Frame 10/26/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/14/2023 Approved TEMISTOCLES CAAL
HVAC-Rough 5/28/2024 Partial Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/27/2024 Not Ready for Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 7/8/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/8/2024 Approved JESUS RODRIGUEZ
Green Building Rough 7/8/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 7/8/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 7/8/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 7/8/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 8/6/2024 Partial Approval JESUS RODRIGUEZ
Insulation 8/6/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 5/21/2025 Approved MICHAEL ALLEN