2340 N VESTAL AVE 90026
Certificate Information: 2340 N VESTAL AVE 90026
- Application / Permit
- 21010-30000-03598
- Plan Check / Job No.
- B21WL03194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU.
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | RICHARD GARCIA |
| Corrections Issued | 8/7/2021 | RICHARD GARCIA |
| Quality Review Completed | 8/18/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/19/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Plan Check Approved | 1/4/2022 | RICHARD GARCIA |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 5/4/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
| CofO Issued | 5/5/2026 | DEROLD HAUFF |
| Permit Finaled | 5/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/31/2021 | RENZ SORIANO |
| ZA Case | Cleared | 9/1/2021 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 10/18/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/21/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | STEVE MELGAR |
| Green Code | Cleared | 11/19/2021 | RICHARD GARCIA |
| BHO/Hillside ordinance | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| BHO/Hillside ordinance | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 9/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 9/28/2022 | Conditional Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 9/28/2022 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 11/1/2022 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/13/2022 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 2/17/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/3/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 11/13/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 11/27/2023 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/12/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/12/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 12/12/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/29/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/29/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/29/2023 | Partial Approval | THOMAS LOGRASSO |
| Sewer | 1/25/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 2/15/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/29/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/8/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/3/2024 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 5/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/25/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 7/25/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 7/25/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 7/25/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Service/Power Release | 7/25/2025 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 4/29/2026 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/29/2026 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/29/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 5/4/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |