2340 N VESTAL AVE 90026

Certificate Information: 2340 N VESTAL AVE 90026

Application / Permit
21010-30000-03598
Plan Check / Job No.
B21WL03194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story ADU.
Permit Issued
Issued on 7/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 RICHARD GARCIA
Corrections Issued 8/7/2021 RICHARD GARCIA
Quality Review Completed 8/18/2021 TARIK SAOUD
Applicant returned to address corrections 11/19/2021 RICHARD GARCIA
Building Plans Picked Up 11/23/2021 APPLICANT
Plan Check Approved 1/4/2022 RICHARD GARCIA
Issued 7/28/2022 APPLICANT
CofO in Progress 5/4/2026 HAMIK HARTOUNIAN
Permit Finaled 5/5/2026 DEROLD HAUFF
CofO Issued 5/5/2026 DEROLD HAUFF
Permit Finaled 5/5/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/27/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/31/2021 RENZ SORIANO
Sewer availability Cleared 8/31/2021 RENZ SORIANO
ZA Case Cleared 9/1/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 10/18/2021 KURT CORRAL
Low Impact Development Cleared 10/21/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/26/2021 STEVE MELGAR
Green Code Cleared 11/19/2021 RICHARD GARCIA
BHO/Hillside ordinance Cleared 12/2/2021 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 12/2/2021 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 12/2/2021 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 12/2/2021 CHRISTOPHER ROCHA
BHO/Hillside ordinance Cleared 12/2/2021 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 9/2/2022 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/15/2022 Partial Approval THOMAS LOGRASSO
Piling/Pier/Caisson 9/15/2022 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 9/28/2022 Conditional Approval THOMAS LOGRASSO
Piling/Pier/Caisson 9/28/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 10/31/2022 Partial Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 11/1/2022 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 12/13/2022 Corrections Issued THOMAS LOGRASSO
Underground Mechanical 2/17/2023 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 3/3/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/13/2023 Corrections Issued THOMAS LOGRASSO
Deputy Wood Construction 11/27/2023 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 12/12/2023 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 12/12/2023 Approved THOMAS LOGRASSO
Green Building Rough 12/12/2023 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 12/12/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 12/29/2023 Approved THOMAS LOGRASSO
Green Building Rough 12/29/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 12/29/2023 Partial Approval THOMAS LOGRASSO
Sewer 1/25/2024 Approved THOMAS LOGRASSO
Insulation 2/15/2024 Approved THOMAS LOGRASSO
Drywall Nailing 2/29/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/8/2024 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/3/2024 Approved LUIS CASTRO
ELECTRICAL-Final 5/5/2025 Approved ALIZAH MAYAGOITIA
Final 7/25/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/25/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 7/25/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 7/25/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 7/25/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV No Gas HAMIK HARTOUNIAN
Service/Power Release 7/25/2025 Approved HAMIK HARTOUNIAN
Smoke Detectors 7/25/2025 Corrections Issued HAMIK HARTOUNIAN
Final 4/29/2026 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/29/2026 Approved HAMIK HARTOUNIAN
Smoke Detectors 4/29/2026 Approved HAMIK HARTOUNIAN
Final 5/4/2026 OK to Issue CofO HAMIK HARTOUNIAN