- (N) 1-story Detached ADU w/ roof trusses. PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | ALFREDO JARA |
| Corrections Issued | 8/5/2021 | ALFREDO JARA |
| Quality Review Completed | 8/20/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/1/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 12/21/2021 | ALFREDO JARA |
| Plan Check Approved | 1/10/2022 | ALFREDO JARA |
| Issued | 1/19/2022 | APPLICANT |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| CofO in Progress | 4/25/2023 | JEREMY TODD |
| Permit Finaled | 5/2/2023 | DANIEL ORRANTE |
| CofO Issued | 5/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| CPC | Cleared | 8/26/2021 | LOUIS ORTEGA |
| CPC | Cleared | 8/26/2021 | LOUIS ORTEGA |
| ZI | Cleared | 8/26/2021 | LOUIS ORTEGA |
| Address approval | Cleared | 8/30/2021 | JEANIE LAM |
| Permit | Cleared | 8/30/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/31/2021 | JEANIE LAM |
| Trees in Parkway | Cleared | 9/23/2021 | JOEL HERNANDEZ |
| Low Impact Development | Cleared | 10/15/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 11/12/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 12/4/2021 | RIDWAN HARDY |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 3/9/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 4/1/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 4/1/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 5/23/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/24/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 6/24/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 6/24/2022 | Approved | EVAN COOPER |
| Shower Pan | 6/24/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/24/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/27/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/27/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/27/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/3/2022 | No Access for Inspection | EVAN COOPER |
| Green Building Rough | 8/3/2022 | No Access for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 8/9/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 8/9/2022 | Approved | EVAN COOPER |
| Green Building Rough | 8/9/2022 | Approved | EVAN COOPER |
| Insulation | 8/19/2022 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 8/19/2022 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 8/31/2022 | Approved | EVAN COOPER |
| Insulation | 8/31/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 11/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 11/22/2022 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 11/22/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 12/2/2022 | Conditional Approval | EVAN COOPER |
| Green Building Final | 12/2/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 12/2/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 12/2/2022 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 12/2/2022 | Partial Inspection | JEREMY TODD |
| Green Building Final | 12/15/2022 | Approved | JEREMY TODD |
| PLUMBING-Final | 12/15/2022 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | JEREMY TODD |
| Service/Power Release | 12/15/2022 | Not Ready for Inspection | JEREMY TODD |
| Special/Order Compliance | 12/15/2022 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | JEREMY TODD |
| Final | 4/3/2023 | Not Ready for Inspection | JEREMY TODD |
| HVAC-Final | 4/3/2023 | Not Ready for Inspection | JEREMY TODD |
| Service/Power Release | 4/3/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 4/3/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 4/12/2023 | Approved | JEREMY TODD |
| Final | 4/12/2023 | Corrections Issued | JEREMY TODD |
| HVAC-Final | 4/12/2023 | Approved | JEREMY TODD |
| Final | 4/24/2023 | OK to Issue CofO | JEREMY TODD |
| Service/Power Release | 4/24/2023 | Approved | JEREMY TODD |