1135-1137 N COMMONWEALTH AVE 90029

Certificate Information: 1135-1137 N COMMONWEALTH AVE 90029

Application / Permit
21010-30000-03576
Plan Check / Job No.
B21WL03162
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 2-story Duplex with attached garages
Permit Issued
Issued on 1/11/2022
Issuing Office
Current Status
CofO Issued on 5/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 RICHARD GARCIA
Corrections Issued 8/10/2021 RICHARD GARCIA
Quality Review Completed 8/23/2021 TARIK SAOUD
Plan Check Approved 1/6/2022 RICHARD GARCIA
Issued 1/11/2022 APPLICANT
Building Plans Picked Up 1/20/2022 APPLICANT
CofO in Progress 4/20/2023 FREDDIE RIVERA
Permit Finaled 5/19/2023 DEROLD HAUFF
CofO Issued 5/19/2023 DEROLD HAUFF
Permit Finaled 5/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 9/2/2021 RUBEN VASQUEZ
ZI Cleared 9/2/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 9/7/2021 RENZ SORIANO
Permit Cleared 9/7/2021 RENZ SORIANO
Sewer availability Cleared 9/7/2021 RENZ SORIANO
Low Impact Development Cleared 11/9/2021 KHAING AYE
Hydrant and Access approval Cleared 11/24/2021 RUEL COLE
Roof/Waste drainage to street Cleared 12/6/2021 JEANETTE VONG
Grading Pre-Inspection Cleared 1/6/2022 RICHARD GARCIA
Green Code Cleared 1/6/2022 RICHARD GARCIA

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/27/2022 Approved FREDDIE RIVERA
Underground Mechanical 4/27/2022 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/5/2022 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/6/2022 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/17/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 7/15/2022 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Conditional Approval FREDDIE RIVERA
HVAC-Rough 8/2/2022 Conditional Approval MICHAEL LEWIS
PLUMBING-Rough 8/19/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/16/2022 Approved FREDDIE RIVERA
Deputy Wood Construction 9/21/2022 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 9/22/2022 Approved FREDDIE RIVERA
Green Building Rough 9/22/2022 Approved FREDDIE RIVERA
Pre-Inspection 9/22/2022 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 9/22/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/12/2022 Partial Approval FREDDIE RIVERA
Insulation 10/28/2022 Approved FREDDIE RIVERA
Drywall Nailing 11/7/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/10/2022 Approved FREDDIE RIVERA
Underground Mechanical 12/15/2022 Approved FREDDIE RIVERA
Gas Test 1/26/2023 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Not Ready FREDDIE RIVERA
ELECTRICAL-Final 2/10/2023 Approved FREDDIE RIVERA
Gas Test 2/10/2023 Approved FREDDIE RIVERA
HVAC-Final 2/10/2023 Approved FREDDIE RIVERA
PLUMBING-Final 2/10/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/10/2023 SGSOV Approved FREDDIE RIVERA
Service/Power Release 2/10/2023 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 2/15/2023 Approved MICHAEL PELHAM
Final 4/12/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/12/2023 Approved FREDDIE RIVERA
Green Building Final 4/12/2023 Approved FREDDIE RIVERA
Smoke Detectors 4/12/2023 Approved FREDDIE RIVERA
Final 4/20/2023 OK to Issue CofO FREDDIE RIVERA
Special/Order Compliance 5/10/2023 Corrections Issued FREDDIE RIVERA