1135-1137 N COMMONWEALTH AVE 90029
Certificate Information: 1135-1137 N COMMONWEALTH AVE 90029
- Application / Permit
- 21010-30000-03576
- Plan Check / Job No.
- B21WL03162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2-story Duplex with attached garages
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 5/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | RICHARD GARCIA |
| Corrections Issued | 8/10/2021 | RICHARD GARCIA |
| Quality Review Completed | 8/23/2021 | TARIK SAOUD |
| Plan Check Approved | 1/6/2022 | RICHARD GARCIA |
| Issued | 1/11/2022 | APPLICANT |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| CofO in Progress | 4/20/2023 | FREDDIE RIVERA |
| Permit Finaled | 5/19/2023 | DEROLD HAUFF |
| CofO Issued | 5/19/2023 | DEROLD HAUFF |
| Permit Finaled | 5/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 9/2/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 9/2/2021 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2021 | RENZ SORIANO |
| Permit | Cleared | 9/7/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/7/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 11/9/2021 | KHAING AYE |
| Hydrant and Access approval | Cleared | 11/24/2021 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 1/6/2022 | RICHARD GARCIA |
| Green Code | Cleared | 1/6/2022 | RICHARD GARCIA |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/27/2022 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 4/27/2022 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 7/15/2022 | Conditional Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Conditional Approval | FREDDIE RIVERA |
| HVAC-Rough | 8/2/2022 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 8/19/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/16/2022 | Approved | FREDDIE RIVERA |
| Deputy Wood Construction | 9/21/2022 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/22/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/22/2022 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 9/22/2022 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 9/22/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/12/2022 | Partial Approval | FREDDIE RIVERA |
| Insulation | 10/28/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/7/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/10/2022 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 12/15/2022 | Approved | FREDDIE RIVERA |
| Gas Test | 1/26/2023 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| ELECTRICAL-Final | 2/10/2023 | Approved | FREDDIE RIVERA |
| Gas Test | 2/10/2023 | Approved | FREDDIE RIVERA |
| HVAC-Final | 2/10/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 2/10/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 2/10/2023 | Not Ready for Inspection | FREDDIE RIVERA |
| Service/Power Release | 2/15/2023 | Approved | MICHAEL PELHAM |
| Final | 4/12/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/12/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 4/12/2023 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/12/2023 | Approved | FREDDIE RIVERA |
| Final | 4/20/2023 | OK to Issue CofO | FREDDIE RIVERA |
| Special/Order Compliance | 5/10/2023 | Corrections Issued | FREDDIE RIVERA |