2350 S GREENFIELD AVE 90064
Certificate Information: 2350 S GREENFIELD AVE 90064
- Application / Permit
- 21010-30000-03504
- Plan Check / Job No.
- B21WL03072
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (2,836 sf) w./ att. 2-car garage (339 sf)
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | REZA HAGHIGHAT |
| Corrections Issued | 8/2/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/19/2021 | TARIK SAOUD |
| Plan Check Approved | 11/18/2021 | REZA HAGHIGHAT |
| Issued | 12/2/2021 | APPLICANT |
| CofO in Progress | 9/26/2022 | JOHN KIDWELL |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | SAUL GARCIA |
| Permit | Cleared | 8/27/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 8/27/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 8/30/2021 | DYLAN SITTIG |
| Specific Plan | Cleared | 8/30/2021 | KEVIN ARUCAN |
| Specific Plan | Cleared | 8/30/2021 | KEVIN ARUCAN |
| Trees in Parkway | Cleared | 10/9/2021 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 10/13/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/15/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | SAUL GARCIA |
| GPI Written Notices | Cleared | 11/18/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 11/18/2021 | REZA HAGHIGHAT |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/26/2022 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 1/26/2022 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Partial Inspection | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 2/10/2022 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 3/4/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/12/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 4/12/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 4/19/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 4/19/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/22/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/26/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 4/26/2022 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 4/26/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 5/4/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/17/2022 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 5/17/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/27/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/17/2022 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| Verify Rec and Parks Fee Memo | 8/31/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 9/9/2022 | Approved | JOHNNY MIRANDA |
| Final | 9/14/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/14/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 9/14/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 9/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 9/14/2022 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 9/14/2022 | Approved | JOHNNY MIRANDA |
| Final | 9/20/2022 | OK to Issue CofO | JOHN KIDWELL |
| PLUMBING-Final | 9/20/2022 | Approved | JOHN KIDWELL |