5457 N TROOST AVE 91601

Certificate Information: 5457 N TROOST AVE 91601

Application / Permit
21010-30000-03305
Plan Check / Job No.
B21WL02946
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU 840 sf unit "B " *** 2 of 2 ***
Permit Issued
Issued on 9/18/2022
Issuing Office
Current Status
CofO Issued on 11/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 RICHARD GARCIA
Corrections Issued 8/6/2021 RICHARD GARCIA
Quality Review Completed 8/18/2021 TARIK SAOUD
Applicant returned to address corrections 7/1/2022 RICHARD GARCIA
Applicant returned to address corrections 8/2/2022 RICHARD GARCIA
Plan Check Approved 8/29/2022 RICHARD GARCIA
Issued 9/18/2022 APPLICANT
Building Plans Picked Up 9/20/2022 APPLICANT
CofO in Progress 11/24/2023 RUBEN SALAS
Permit Finaled 11/24/2023 RUBEN SALAS
CofO Issued 11/24/2023 RUBEN SALAS
Permit Finaled 11/24/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/20/2021 GABRIEL ROBLES
Sewer availability Cleared 10/20/2021 GABRIEL ROBLES
Address approval Cleared 1/4/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY
ZI Cleared 2/15/2022 RUBEN VASQUEZ
Specific Plan Cleared 2/22/2022 CORREY KITCHENS
ZI Cleared 2/23/2022 CORREY KITCHENS
Construction near power lines Cleared 5/23/2022 RIDWAN HARDY
Low Impact Development Cleared 7/8/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/11/2022 JOSE DUARTE-DIAZ
Green Code Cleared 8/29/2022 RICHARD GARCIA

Contact Information

Contractor Lau Eric; Lic. No.: 664997-B 18500 KINGSBURY ST      PORTER RANCH, CA 91326
Engineer Sparks,, David Michael; Lic. No.: C65739 4116 EAGLE RIDGE WAY      CASTLE ROCK, CO 80104

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2023 Corrections Issued JACK KARGODORIAN
Pre-Inspection 2/22/2023 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 4/10/2023 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/14/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 6/26/2023 Partial Inspection DAVID MATSON
Green Building Rough 6/26/2023 Approved DAVID MATSON
Interior/Exterior Lathing 6/26/2023 Partial Approval DAVID MATSON
MERV13>=Rough 6/26/2023 Approved DAVID MATSON
Verify Sprinkler Sign Off 6/26/2023 Approved DAVID MATSON
ELECTRICAL-Rough 6/27/2023 Approved THOMAS FINNILA
HVAC-Rough 6/27/2023 Approved THOMAS FINNILA
PLUMBING-Rough 6/27/2023 Approved THOMAS FINNILA
Insulation 7/7/2023 Approved JACK KARGODORIAN
Drywall Nailing 7/17/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/10/2023 Partial Approval JACK KARGODORIAN
Shower Pan 8/10/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 8/31/2023 Approved JACK KARGODORIAN
Underground Mechanical 9/20/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/23/2023 Approved JUAN VALENZUELA
Final 10/23/2023 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 10/23/2023 Approved JUAN VALENZUELA
Green Building Final 10/23/2023 Approved JUAN VALENZUELA
MERV13>=Final 10/23/2023 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved JUAN VALENZUELA
Service/Power Release 10/23/2023 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 10/23/2023 Approved JUAN VALENZUELA
Final 10/30/2023 Conditional Approval RUBEN SALAS
MERV13>=Final 10/30/2023 Approved RUBEN SALAS
Service/Power Release 10/30/2023 Not Ready for Inspection RUBEN SALAS