5459 N TROOST AVE 91601
Certificate Information: 5459 N TROOST AVE 91601
- Application / Permit
- 21010-30000-03304
- Plan Check / Job No.
- B21WL02946
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU (Unit "A" 840sf) *** 1 of 2 ***
- Permit Issued
- Issued on 9/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | RICHARD GARCIA |
| Corrections Issued | 8/6/2021 | RICHARD GARCIA |
| Quality Review Completed | 8/18/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/1/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 8/2/2022 | RICHARD GARCIA |
| Plan Check Approved | 8/29/2022 | RICHARD GARCIA |
| Issued | 9/18/2022 | APPLICANT |
| Building Plans Picked Up | 9/20/2022 | APPLICANT |
| CofO in Progress | 11/24/2023 | RUBEN SALAS |
| Permit Finaled | 11/24/2023 | RUBEN SALAS |
| CofO Issued | 11/24/2023 | RUBEN SALAS |
| Permit Finaled | 11/24/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/20/2021 | GABRIEL ROBLES |
| Address approval | Cleared | 1/4/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/29/2022 | JOHN CONNEALLY |
| ZI | Cleared | 2/15/2022 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 2/22/2022 | CORREY KITCHENS |
| ZI | Cleared | 2/23/2022 | CORREY KITCHENS |
| Construction near power lines | Cleared | 5/23/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/8/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | JOSE DUARTE-DIAZ |
| Green Code | Cleared | 8/29/2022 | RICHARD GARCIA |
Contact Information
| Contractor | Lau Eric; Lic. No.: 664997-B | 18500 KINGSBURY ST PORTER RANCH, CA 91326 |
| Engineer | Sparks,, David Michael; Lic. No.: C65739 | 4116 EAGLE RIDGE WAY CASTLE ROCK, CO 80104 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/17/2023 | Corrections Issued | JACK KARGODORIAN |
| Pre-Inspection | 2/22/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 4/10/2023 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/26/2023 | Partial Inspection | DAVID MATSON |
| Green Building Rough | 6/26/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 6/26/2023 | Partial Approval | DAVID MATSON |
| MERV13>=Rough | 6/26/2023 | Approved | DAVID MATSON |
| Verify Sprinkler Sign Off | 6/26/2023 | Approved | DAVID MATSON |
| ELECTRICAL-Rough | 6/27/2023 | Approved | THOMAS FINNILA |
| HVAC-Rough | 6/27/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 6/27/2023 | Approved | THOMAS FINNILA |
| Insulation | 7/7/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 7/17/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 8/10/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/31/2023 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 9/20/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | JUAN VALENZUELA |
| Final | 10/23/2023 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/23/2023 | Approved | JUAN VALENZUELA |
| Green Building Final | 10/23/2023 | Approved | JUAN VALENZUELA |
| MERV13>=Final | 10/23/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 10/23/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 10/23/2023 | Approved | JUAN VALENZUELA |
| Final | 10/30/2023 | Conditional Approval | RUBEN SALAS |
| MERV13>=Final | 10/30/2023 | Approved | RUBEN SALAS |
| Service/Power Release | 10/30/2023 | Not Ready for Inspection | RUBEN SALAS |