5723 N BECKFORD AVE 91356
Certificate Information: 5723 N BECKFORD AVE 91356
- Application / Permit
- 21010-30000-03273
- Plan Check / Job No.
- B21WL02893
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story detached ADU (1,200 sf) at rear of the lot per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/30/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | REZA HAGHIGHAT |
| Corrections Issued | 7/20/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/10/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/20/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 11/18/2021 | REZA HAGHIGHAT |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Issued | 11/30/2021 | APPLICANT |
| CofO in Progress | 8/19/2022 | SEAN HAUPT |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
| CofO Issued | 8/27/2022 | MICHAEL SMITH |
| Permit Finaled | 8/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/21/2021 | CARLOS AGUILERA |
| Disturb/Remove Protected Trees | Cleared | 10/20/2021 | HECTOR BANUELOS |
| Low Impact Development | Cleared | 10/21/2021 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 11/3/2021 | MATTHEW CRAIG |
Contact Information
| Architect | , ; Lic. No.: C35150 | 2355 WESTWOOD BLVD # 834 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/16/2021 | No Access for Inspection | SEAN HAUPT |
| Underground Mechanical | 12/20/2021 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 1/3/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 1/3/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Approved | SEAN HAUPT |
| Pre-Inspection | 2/23/2022 | Partial Approval | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 3/1/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 3/24/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | SEAN HAUPT |
| MERV13>=Rough | 3/24/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 3/24/2022 | Approved | SEAN HAUPT |
| Insulation | 4/1/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/1/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/11/2022 | Approved | SEAN HAUPT |
| Shower Pan | 4/18/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/28/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/13/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 6/13/2022 | Approved | SEAN HAUPT |
| Final | 6/13/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 6/13/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 6/13/2022 | Approved | SEAN HAUPT |
| MERV13>=Final | 6/13/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 6/13/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 6/13/2022 | Approved | SEAN HAUPT |
| Final | 8/18/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 8/18/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 8/18/2022 | Approved | SEAN HAUPT |