1047 N CORSICA DR 90272
Certificate Information: 1047 N CORSICA DR 90272
- Application / Permit
- 21010-30000-03257
- Plan Check / Job No.
- B21WL02880
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) two-story single family residence w/ basement and attached garage. type V construction *** 1 of 2 ***
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 7/20/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 8/10/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 9/1/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 10/22/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 11/24/2021 | FELIPE HERNANDEZ |
| Issued | 12/2/2021 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| CofO in Progress | 10/25/2024 | ARAM AVEDISIAN |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
| CofO Issued | 10/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 7/27/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | TRACY TATE |
| Sewer availability | Cleared | 8/11/2021 | TRACY TATE |
| GPI Written Notices | Cleared | 9/1/2021 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 9/1/2021 | FELIPE HERNANDEZ |
| Hydrant and Access approval | Cleared | 9/20/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/14/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | TRACY TATE |
| Trees in Parkway | Cleared | 10/15/2021 | JOEL HERNANDEZ |
Contact Information
| Architect | , ; Lic. No.: C34496 | LOS ANGELES, CA 90035 |
| Contractor | Shore Real Estate Development; Lic. No.: 914609-B | 270 N CANON DRIVE 3RD FLOOR BEVERLY HILLS, CA 90210 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 3/4/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Shotcrete | 3/8/2022 | Approved | MICHAEL PELHAM |
| PLUMBING-Rough | 3/30/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/14/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/18/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 5/31/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/15/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/17/2022 | Approved | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 9/15/2022 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 10/5/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/15/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 1/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 4/3/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 4/17/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/1/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/1/2023 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/2/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/4/2023 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/4/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/10/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/10/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/18/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/18/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/30/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 5/30/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 6/13/2023 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/30/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/10/2023 | Approved | OGANES TARAKHCHYAN |
| Sewer | 12/19/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/23/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/8/2024 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/20/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/23/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 7/25/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/26/2024 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 7/26/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 7/26/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/23/2024 | Approved | JESUS RODRIGUEZ |
| Final | 10/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 10/23/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/23/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Smoke Detectors | 10/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 10/25/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 10/25/2024 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 10/25/2024 | Approved | ARAM AVEDISIAN |