1047 N CORSICA DR 90272

Certificate Information: 1047 N CORSICA DR 90272

Application / Permit
21010-30000-03257
Plan Check / Job No.
B21WL02880
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) two-story single family residence w/ basement and attached garage. type V construction *** 1 of 2 ***
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 FELIPE HERNANDEZ
Corrections Issued 7/20/2021 FELIPE HERNANDEZ
Quality Review Completed 8/10/2021 TARIK SAOUD
Applicant returned to address corrections 9/1/2021 FELIPE HERNANDEZ
Plan Check Approved 10/22/2021 FELIPE HERNANDEZ
Plan Check Approved 11/24/2021 FELIPE HERNANDEZ
Issued 12/2/2021 APPLICANT
Building Plans Picked Up 5/3/2022 APPLICANT
CofO in Progress 10/25/2024 ARAM AVEDISIAN
Permit Finaled 10/30/2024 RICHARD STEINBACH
CofO Issued 10/30/2024 RICHARD STEINBACH
Permit Finaled 10/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 7/27/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/11/2021 TRACY TATE
Sewer availability Cleared 8/11/2021 TRACY TATE
GPI Written Notices Cleared 9/1/2021 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 9/1/2021 FELIPE HERNANDEZ
Hydrant and Access approval Cleared 9/20/2021 MATTHEW CRAIG
Low Impact Development Cleared 10/14/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/14/2021 TRACY TATE
Trees in Parkway Cleared 10/15/2021 JOEL HERNANDEZ

Contact Information

Architect , ; Lic. No.: C34496       LOS ANGELES, CA 90035
Contractor Shore Real Estate Development; Lic. No.: 914609-B 270 N CANON DRIVE 3RD FLOOR      BEVERLY HILLS, CA 90210
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/9/2022 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 3/4/2022 Partial Approval JUAN VALENZUELA
Deputy Shotcrete 3/8/2022 Approved MICHAEL PELHAM
PLUMBING-Rough 3/30/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 4/14/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/18/2022 Partial Approval JUAN VALENZUELA
Deputy Steel/Welding 5/31/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 6/15/2022 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/17/2022 Approved JUAN VALENZUELA
Footing/Foundation/Slab 6/17/2022 Approved JUAN VALENZUELA
Deputy Drilled-In Anchors 9/15/2022 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 10/5/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 11/15/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 1/19/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 4/3/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Approved KEVIN SARGSYAN
HVAC-Rough 4/17/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 5/1/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/1/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/2/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/4/2023 Approved OGANES TARAKHCHYAN
Wood Frame 5/4/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/10/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 5/10/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/10/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 5/10/2023 Approved OGANES TARAKHCHYAN
Insulation 5/18/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/18/2023 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 5/30/2023 Approved GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/30/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Shower Pan 6/13/2023 Approved KENNETH NAGLE
Interior/Exterior Lathing 6/30/2023 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/10/2023 Approved OGANES TARAKHCHYAN
Sewer 12/19/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 1/23/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 2/8/2024 Partial Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 6/20/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 7/23/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Final 7/25/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Final 7/26/2024 Partial Approval ARAM AVEDISIAN
Gas Test 7/26/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 7/26/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 10/2/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 10/23/2024 Approved JESUS RODRIGUEZ
Final 10/23/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/23/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 10/23/2024 Conditional Approval JESUS RODRIGUEZ
Smoke Detectors 10/23/2024 Corrections Issued JESUS RODRIGUEZ
Final 10/25/2024 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 10/25/2024 Approved ARAM AVEDISIAN
Smoke Detectors 10/25/2024 Approved ARAM AVEDISIAN