124-124 1/2 N MANHATTAN PL 90004
Certificate Information: 124-124 1/2 N MANHATTAN PL 90004
- Application / Permit
- 21010-30000-03253
- Plan Check / Job No.
- B21WL02868
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex (2,481 sf) w./ 2 att. 2-car garages (688 sf) at front of the lot ; Unit A = 1,143 sf ; Att. garage = 359 sf ; Unit B = 1,338 sf ; Att. garage = 329 sf ;
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | REZA HAGHIGHAT |
| Corrections Issued | 7/19/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 8/3/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 11/12/2021 | REZA HAGHIGHAT |
| Issued | 11/12/2021 | APPLICANT |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| CofO in Progress | 1/10/2024 | JEFFREY MEAD |
| Permit Finaled | 2/12/2024 | DEROLD HAUFF |
| CofO Issued | 2/12/2024 | DEROLD HAUFF |
| Permit Finaled | 2/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/11/2021 | STEVE MELGAR |
| Historic Resource Verification | Cleared | 9/21/2021 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 9/21/2021 | GRACIELA ACOSTA |
| ZA Case | Cleared | 9/23/2021 | LOUIS ORTEGA |
| Frnt yard landscape/Water mgmt | Cleared | 9/30/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 10/7/2021 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 10/21/2021 | RUEL COLE |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | STEVE MELGAR |
| Building over 36-ft | Cleared | 11/12/2021 | CALOSHA APPROVED |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/19/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/2/2022 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 2/7/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 2/10/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Approved | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Underground Mechanical | 2/15/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/1/2022 | Approved | AMY COLIN |
| Sewer | 3/14/2022 | Approved | SHAVONNE ESPINOZA |
| Underground Mechanical | 3/14/2022 | Approved | SHAVONNE ESPINOZA |
| Deputy Wood Construction | 4/12/2022 | Conditional Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Deputy Reinf. Concrete | 5/3/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Partial Inspection | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 7/6/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/20/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 7/28/2022 | Approved | JEFFREY MEAD |
| Shower Pan | 8/10/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 8/24/2022 | Corrections Issued | JEFFREY MEAD |
| Sewer | 10/5/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/14/2022 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 10/14/2022 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 10/14/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 11/2/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Insulation | 11/2/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/2/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/14/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 11/21/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 11/29/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/22/2023 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Structural Steel Frame | 2/22/2023 | Partial Approval | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 2/22/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/23/2023 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 3/24/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 3/24/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 3/29/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 3/29/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/3/2023 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 5/16/2023 | Corrections Issued | JEFFREY MEAD |
| Service/Power Release | 11/6/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/3/2024 | Approved | JEFFREY MEAD |
| Final | 1/3/2024 | Conditional Approval | JEFFREY MEAD |
| Green Building Final | 1/3/2024 | Approved | JEFFREY MEAD |
| Smoke Detectors | 1/3/2024 | Approved | JEFFREY MEAD |
| Structural Steel Frame | 1/3/2024 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 1/3/2024 | Approved | JEFFREY MEAD |
| Final | 1/5/2024 | Corrections Issued | JEFFREY MEAD |
| Final | 1/9/2024 | OK to Issue CofO | JEFFREY MEAD |