10080 W SUNSET BLVD 90077

Certificate Information: 10080 W SUNSET BLVD 90077

Application / Permit
21010-30000-03155
Plan Check / Job No.
B21WL02796
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
New 1-story guard house
Permit Issued
Issued on 5/23/2022
Issuing Office
West Los Angeles
Current Status
Issued on 5/23/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/24/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 REZA HAGHIGHAT
Corrections Issued 7/14/2021 REZA HAGHIGHAT
Quality Review Completed 7/29/2021 CHIHARU SUZUKI
Applicant returned to address corrections 12/29/2021 REZA HAGHIGHAT
Applicant returned to address corrections 1/21/2022 REZA HAGHIGHAT
Applicant returned to address corrections 1/27/2022 REZA HAGHIGHAT
Applicant returned to address corrections 3/9/2022 REZA HAGHIGHAT
Applicant returned to address corrections 4/1/2022 REZA HAGHIGHAT
Applicant returned to address corrections 4/29/2022 REZA HAGHIGHAT
Applicant returned to address corrections 5/6/2022 REZA HAGHIGHAT
Plan Check Approved 5/8/2022 REZA HAGHIGHAT
Issued 5/23/2022 APPLICANT
Building Plans Picked Up 5/24/2022 APPLICANT
Permit Expired-Status Void 6/14/2024 MICHAEL PELHAM
Re-Activate Permit 6/24/2025 MICHAEL PELHAM

Permit Application Clearance Information

ZA Case Cleared 11/4/2021 RICHARD REASER
ZA Case Cleared 11/4/2021 RICHARD REASER
Low Impact Development Cleared 3/30/2022 MARCO SANCHEZ
Hydrant and Access approval Cleared 4/7/2022 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 4/12/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/12/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/12/2022 HISASHI KOBAYAKAWA
Watercourse Cleared 4/12/2022 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 5/8/2022 REZA HAGHIGHAT

Contact Information

Architect Ulinskas,, Geddes J; Lic. No.: C27862 771 CLEMENTINA STREET      SAN FRANCISCO, CA 94103
Contractor J D Group Construction Company Inc; Lic. No.: 801797-B 1537 PONTIUS AVENUE SUITE B      LOS ANGELES, CA 90025
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/14/2024 Not Ready for Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Approved CHRISTOPHER WILSON
PLUMBING-Rough 8/25/2025 Approved DANIEL VERA
PLUMBING-Rough 8/27/2025 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 1/23/2026 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 1/23/2026 Conditional Approval CHRISTOPHER WILSON
FLOOD-Proofing Certificate 1/23/2026 Approved CHRISTOPHER WILSON
Green Building Rough 1/23/2026 Approved CHRISTOPHER WILSON
HVAC-Rough 1/23/2026 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 1/23/2026 Approved CHRISTOPHER WILSON
PLUMBING-Rough 1/23/2026 Approved CHRISTOPHER WILSON
Insulation 1/28/2026 Approved CHRISTOPHER WILSON
Drywall Nailing 2/2/2026 Approved CHRISTOPHER WILSON
Pre-Inspection 5/6/2026 Corrections Issued RYAN SALAZAR