Pre-Inspection
|
8/29/2022
|
Approved
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
9/26/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Piling/Pier/Caisson
|
9/26/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Pre-Inspection
|
9/26/2022
|
Not Ready for Inspection
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
9/27/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Piling/Pier/Caisson
|
9/27/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Pre-Inspection
|
9/27/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
11/29/2022
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
11/29/2022
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
12/7/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Piling/Pier/Caisson
|
12/7/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
12/8/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Underground Mechanical
|
12/20/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
2/1/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
2/1/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
2/6/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
2/6/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Piling/Pier/Caisson
|
2/6/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
2/7/2023
|
Approved
|
BRENDAN LOONEY
|
|
Deputy Shotcrete
|
2/9/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
PLUMBING-Rough
|
2/21/2023
|
Partial Approval
|
KENNETH NAGLE
|
|
Excavation/Setback/Form/Re-Bar
|
2/27/2023
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Piling/Pier/Caisson
|
2/27/2023
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Reinforced Masonry Frame
|
2/27/2023
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Underground Mechanical
|
2/27/2023
|
Not Ready for Inspection
|
OGANES TARAKHCHYAN
|
|
Pre-Inspection
|
3/2/2023
|
Approved
|
BRENDAN LOONEY
|
|
Structural Steel Frame
|
3/2/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Reinf. Concrete
|
3/6/2023
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
3/7/2023
|
Not Ready for Inspection
|
DAVID FEILER
|
|
Footing/Foundation/Slab
|
3/7/2023
|
Not Ready for Inspection
|
DAVID FEILER
|
|
Structural Steel Frame
|
3/7/2023
|
Not Ready for Inspection
|
DAVID FEILER
|
|
Excavation/Setback/Form/Re-Bar
|
3/8/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Structural Steel Frame
|
3/8/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
3/9/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Structural Steel Frame
|
3/9/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Steel/Welding
|
3/28/2023
|
Conditional Approval
|
BRENDAN LOONEY
|
|
BUILDING-Rough-Frame
|
4/10/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Green Building Rough
|
4/10/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Verify Sprinkler Sign Off
|
4/10/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Wood Frame
|
4/10/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Deputy Wood Construction
|
4/11/2023
|
Conditional Approval
|
STEPHANIE SWANSON
|
|
BUILDING-Rough-Frame
|
4/13/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Verify Sprinkler Sign Off
|
4/13/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Wood Frame
|
4/13/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Deputy Steel/Welding
|
4/21/2023
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Deputy Steel/Welding
|
4/25/2023
|
No Access for Inspection
|
KENNETH NAGLE
|
|
Footing/Foundation/Slab
|
5/4/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
5/10/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Excavation/Setback/Form/Re-Bar
|
5/11/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Steel/Welding
|
5/15/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/16/2023
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Drilled-In Anchors
|
5/17/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
5/17/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/22/2023
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
6/1/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2023
|
Partial Approval
|
KENNETH NAGLE
|
|
Pre-Inspection
|
6/26/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
6/27/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/29/2023
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Steel/Welding
|
7/11/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Pre-Inspection
|
7/20/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Pre-Inspection
|
7/31/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Pre-Inspection
|
8/11/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Sewer
|
8/17/2023
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Shower Pan
|
8/17/2023
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/18/2023
|
Corrections Issued
|
EVAN COOPER
|
|
Deputy Steel/Welding
|
8/22/2023
|
Conditional Approval
|
EVAN COOPER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2023
|
Partial Approval
|
EVAN COOPER
|
|
HVAC-Rough
|
8/23/2023
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Sewer
|
8/23/2023
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Shower Pan
|
8/23/2023
|
Approved
|
EVAN COOPER
|
|
HVAC-Rough
|
8/28/2023
|
Corrections Issued
|
EVAN COOPER
|
|
PLUMBING-Rough
|
8/28/2023
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Sewer
|
8/28/2023
|
Approved
|
EVAN COOPER
|
|
Underground Mechanical
|
8/28/2023
|
Partial Approval
|
EVAN COOPER
|
|
PLUMBING-Rough
|
9/7/2023
|
Approved
|
EVAN COOPER
|
|
Pre-Inspection
|
9/7/2023
|
Approved
|
EVAN COOPER
|
|
HVAC-Rough
|
9/13/2023
|
Approved
|
EVAN COOPER
|
|
Insulation
|
10/30/2023
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Pre-Inspection
|
10/30/2023
|
Approved
|
EVAN COOPER
|
|
Interior/Exterior Lathing
|
11/7/2023
|
Corrections Issued
|
EVAN COOPER
|
|
ELECTRICAL-Rough
|
11/20/2023
|
Approved
|
EVAN COOPER
|
|
BUILDING-Rough-Frame
|
11/21/2023
|
Approved
|
EVAN COOPER
|
|
ELECTRICAL-Rough
|
11/21/2023
|
Approved
|
EVAN COOPER
|
|
Green Building Rough
|
11/21/2023
|
Approved
|
EVAN COOPER
|
|
Interior/Exterior Lathing
|
11/21/2023
|
Partial Approval
|
EVAN COOPER
|
|
Verify Sprinkler Sign Off
|
11/21/2023
|
Approved
|
EVAN COOPER
|
|
Insulation
|
12/13/2023
|
Corrections Issued
|
EVAN COOPER
|
|
Interior/Exterior Lathing
|
12/13/2023
|
Approved
|
EVAN COOPER
|
|
Drywall Nailing
|
12/28/2023
|
Approved
|
EVAN COOPER
|
|
Gas Test
|
8/13/2024
|
Approved
|
EVAN COOPER
|
|
PLUMBING-Final
|
8/13/2024
|
Approved
|
EVAN COOPER
|
|
SGSOV-Seismic Gas S/O Valve
|
8/13/2024
|
SGSOV Approved
|
EVAN COOPER
|
|
ELECTRICAL-Final
|
8/15/2024
|
Approved
|
EVAN COOPER
|
|
HVAC-Final
|
8/21/2024
|
Corrections Issued
|
EVAN COOPER
|
|
Verify Rec and Parks Fee Memo
|
8/21/2024
|
Approved
|
EVAN COOPER
|
|
HVAC-Final
|
9/6/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
HVAC-Final
|
9/16/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
10/8/2024
|
Corrections Issued
|
EVAN COOPER
|
|
Footing/Foundation/Slab
|
10/8/2024
|
Approved
|
EVAN COOPER
|
|
Green Building Final
|
10/8/2024
|
Approved
|
EVAN COOPER
|
|
Reinforced Concrete Frame
|
10/8/2024
|
Approved
|
EVAN COOPER
|
|
Service/Power Release
|
10/8/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Smoke Detectors
|
10/8/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
10/17/2024
|
Corrections Issued
|
EVAN COOPER
|
|
Service/Power Release
|
10/17/2024
|
Not Ready for Inspection
|
EVAN COOPER
|
|
Final
|
10/24/2024
|
Conditional Approval
|
EVAN COOPER
|
|
Service/Power Release
|
10/24/2024
|
Approved
|
EVAN COOPER
|
|
Final
|
11/4/2024
|
Corrections Issued
|
EVAN COOPER
|