12405 W IDAHO AVE 90025
Certificate Information: 12405 W IDAHO AVE 90025
- Application / Permit
- 21010-30000-03088
- Plan Check / Job No.
- B21WL02719
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached ADU per LAMC 12.22 A.33 (c), and (d) with Roof Truss
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | DAVID CASTILLO |
| Corrections Issued | 7/13/2021 | DAVID CASTILLO |
| Quality Review Completed | 8/2/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/27/2021 | DAVID CASTILLO |
| Plan Check Approved | 12/1/2021 | DAVID CASTILLO |
| Issued | 12/1/2021 | APPLICANT |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| CofO in Progress | 3/29/2023 | CLAYTON GRAHAM |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
| CofO Issued | 4/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | ANTHONY MAINEZ |
| Highway dedication | Cleared | 8/11/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/11/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 9/1/2021 | PETE EYRE |
| Construction within easement | Cleared | 9/30/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/8/2021 | SUNG JOON WON |
| Hydrant and Access approval | Cleared | 10/21/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | ANTHONY MAINEZ |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 4/29/2022 | Conditional Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 4/29/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/5/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/5/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/5/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 5/24/2022 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 6/1/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/8/2022 | Approved | KENNETH NAGLE |
| Insulation | 6/8/2022 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 9/6/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 11/10/2022 | Partial Approval | ASHLEY THOMPSON |
| Gas Test | 11/10/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 11/10/2022 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 12/2/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 12/2/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/19/2023 | No Access for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 1/19/2023 | No Access for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 1/26/2023 | Corrections Issued | JULIAN AMAYA |
| Final | 2/1/2023 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 2/1/2023 | Approved | DAVID FEILER |
| Green Building Final | 2/1/2023 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 2/1/2023 | Partial Approval | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 2/1/2023 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 2/1/2023 | Approved | DAVID FEILER |
| Final | 2/3/2023 | Corrections Issued | DAVID FEILER |
| Final | 2/17/2023 | Corrections Issued | DAVID FEILER |
| Green Building Final | 2/17/2023 | No Access for Inspection | DAVID FEILER |
| Service/Power Release | 2/17/2023 | No Access for Inspection | DAVID FEILER |
| Final | 3/21/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 3/21/2023 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 3/21/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/29/2023 | Approved | CLAYTON GRAHAM |
| Final | 3/29/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| HVAC-Final | 3/29/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 3/29/2023 | Approved | CLAYTON GRAHAM |