12405 W IDAHO AVE 90025

Certificate Information: 12405 W IDAHO AVE 90025

Application / Permit
21010-30000-03088
Plan Check / Job No.
B21WL02719
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached ADU per LAMC 12.22 A.33 (c), and (d) with Roof Truss
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 DAVID CASTILLO
Corrections Issued 7/13/2021 DAVID CASTILLO
Quality Review Completed 8/2/2021 CHIHARU SUZUKI
Applicant returned to address corrections 10/27/2021 DAVID CASTILLO
Plan Check Approved 12/1/2021 DAVID CASTILLO
Issued 12/1/2021 APPLICANT
Building Plans Picked Up 12/6/2021 APPLICANT
CofO in Progress 3/29/2023 CLAYTON GRAHAM
Permit Finaled 4/14/2023 DANIEL ORRANTE
CofO Issued 4/14/2023 DANIEL ORRANTE
Permit Finaled 4/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/10/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 8/11/2021 ANTHONY MAINEZ
Highway dedication Cleared 8/11/2021 ANTHONY MAINEZ
Sewer availability Cleared 8/11/2021 ANTHONY MAINEZ
Specific Plan Cleared 9/1/2021 PETE EYRE
Construction within easement Cleared 9/30/2021 RIDWAN HARDY
Low Impact Development Cleared 10/8/2021 SUNG JOON WON
Hydrant and Access approval Cleared 10/21/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 10/21/2021 ANTHONY MAINEZ

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/21/2022 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/25/2022 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 4/29/2022 Conditional Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Approved OGANES TARAKHCHYAN
Wood Frame 4/29/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/5/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 5/5/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/5/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/24/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 5/24/2022 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 5/24/2022 Approved OGANES TARAKHCHYAN
Insulation 6/1/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 6/8/2022 Approved KENNETH NAGLE
Insulation 6/8/2022 Approved KENNETH NAGLE
Interior/Exterior Lathing 6/14/2022 Partial Approval STEPHANIE SWANSON
Sewer 9/6/2022 Approved JOHN KIDWELL
ELECTRICAL-Final 11/10/2022 Partial Approval ASHLEY THOMPSON
Gas Test 11/10/2022 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 11/10/2022 Corrections Issued ASHLEY THOMPSON
Gas Test 12/2/2022 Approved ASHLEY THOMPSON
PLUMBING-Final 12/2/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 1/19/2023 No Access for Inspection CLAYTON GRAHAM
HVAC-Final 1/19/2023 No Access for Inspection CLAYTON GRAHAM
HVAC-Final 1/26/2023 Corrections Issued JULIAN AMAYA
Final 2/1/2023 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 2/1/2023 Approved DAVID FEILER
Green Building Final 2/1/2023 Corrections Issued DAVID FEILER
HVAC-Final 2/1/2023 Partial Approval DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Approved DAVID FEILER
Service/Power Release 2/1/2023 Not Ready for Inspection DAVID FEILER
Smoke Detectors 2/1/2023 Approved DAVID FEILER
Final 2/3/2023 Corrections Issued DAVID FEILER
Final 2/17/2023 Corrections Issued DAVID FEILER
Green Building Final 2/17/2023 No Access for Inspection DAVID FEILER
Service/Power Release 2/17/2023 No Access for Inspection DAVID FEILER
Final 3/21/2023 Not Ready for Inspection ASHLEY THOMPSON
Green Building Final 3/21/2023 Approved ASHLEY THOMPSON
Service/Power Release 3/21/2023 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 3/29/2023 Approved CLAYTON GRAHAM
Final 3/29/2023 OK to Issue CofO CLAYTON GRAHAM
HVAC-Final 3/29/2023 Approved CLAYTON GRAHAM
Service/Power Release 3/29/2023 Approved CLAYTON GRAHAM