950 N MORAGA DR 90049

Certificate Information: 950 N MORAGA DR 90049

Application / Permit
21010-30000-02982
Plan Check / Job No.
B21WL02626
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
New ALQ
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
CofO in Progress on 6/3/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 TARIK SAOUD
Corrections Issued 7/4/2021 TARIK SAOUD
Quality Review Completed 7/8/2021 CHIHARU SUZUKI
Plans on Hold 12/2/2021 TARIK SAOUD
Hold Released 2/4/2022 TARIK SAOUD
Plans on Hold 2/4/2022 TARIK SAOUD
Hold Released 2/9/2022 CHIHARU SUZUKI
Plans on Hold 2/24/2022 CHIHARU SUZUKI
Hold Released 4/5/2022 CHIHARU SUZUKI
Plans on Hold 4/28/2022 CHIHARU SUZUKI
Hold Released 5/10/2022 CHIHARU SUZUKI
Plan Check Approved 5/10/2022 CHIHARU SUZUKI
Issued 5/10/2022 APPLICANT
Building Plans Picked Up 5/11/2022 APPLICANT
CofO in Progress 6/3/2026 EVAN COOPER

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/24/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 9/24/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 9/24/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 9/24/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 9/24/2021 DINAH GARIN
Sewer availability Cleared 9/24/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/28/2021 DINAH GARIN
Hydrant and Access approval Cleared 12/7/2021 ROBERT DUFF
Low Impact Development Cleared 1/13/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/8/2022 DINAH GARIN
Watercourse Cleared 3/9/2022 TERRY PHAN
Excavation more than 5-ft deep Cleared 4/28/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 4/28/2022 TARIK SAOUD

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/29/2022 Partial Approval CARLOS MATAMOROS
FLOOD-Proofing Certificate 10/21/2022 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 10/21/2022 Partial Approval CARLOS MATAMOROS
Green Building Rough 10/21/2022 Not Ready for Inspection CARLOS MATAMOROS
Piling/Pier/Caisson 10/21/2022 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 10/21/2022 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/21/2022 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/5/2022 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 12/5/2022 Partial Approval CARLOS MATAMOROS
Verify Sprinkler Sign Off 12/5/2022 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 3/28/2023 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 3/28/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 9/11/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 9/11/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 9/18/2023 Conditional Approval MICHAEL PELHAM
Underground Mechanical 10/4/2023 Corrections Issued CARLOS MATAMOROS
Reinforced Concrete Frame 10/16/2023 Conditional Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 10/17/2023 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 10/20/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 10/20/2023 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 11/21/2023 Partial Approval CARLOS MATAMOROS
Underground Mechanical 11/21/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 11/22/2023 Conditional Approval CARLOS MATAMOROS
Shower Pan 4/8/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 4/22/2024 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 4/26/2024 Corrections Issued CARLOS MATAMOROS
Green Building Rough 4/26/2024 Approved CARLOS MATAMOROS
HVAC-Rough 4/26/2024 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 4/26/2024 Corrections Issued CARLOS MATAMOROS
Verify Sprinkler Sign Off 4/26/2024 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 5/10/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 5/10/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 5/10/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 5/16/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 5/16/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 5/16/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 5/23/2024 Approved CARLOS MATAMOROS
Drywall Nailing 5/30/2024 Corrections Issued TEMISTOCLES CAAL
Special/Order Compliance 5/30/2024 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 6/24/2024 Approved CARLOS MATAMOROS
Reinforced Concrete Frame 6/24/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 6/24/2024 Approved CARLOS MATAMOROS
Underground Mechanical 8/27/2024 Partial Approval CARLOS MATAMOROS
Special/Order Compliance 10/17/2024 Corrections Issued CARLOS MATAMOROS
Underground Mechanical 10/23/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 1/31/2025 Corrections Issued CARLOS MATAMOROS
Wood Frame 1/31/2025 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 2/24/2025 Approved STEPHANIE SWANSON
Insulation 2/24/2025 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 2/24/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Final 7/30/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 7/30/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 7/30/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 7/30/2025 Not Ready for Inspection DANIEL VERA
Final 8/8/2025 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Not Ready CARLOS MATAMOROS
ELECTRICAL-Final 9/16/2025 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/16/2025 Not Ready for Inspection CARLOS MATAMOROS
Special/Order Compliance 9/16/2025 Corrections Issued MICHAEL PELHAM
HVAC-Rough 10/30/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 10/30/2025 Not Ready for Inspection CARLOS MATAMOROS
Special/Order Compliance 10/30/2025 Partial Inspection SEAN HAUPT
HVAC-Final 11/5/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 11/5/2025 Not Ready for Inspection CARLOS MATAMOROS
Special/Order Compliance 11/5/2025 Partial Inspection ANDREW NAVE
ELECTRICAL-Final 1/9/2026 Approved EVAN COOPER
Final 1/13/2026 Corrections Issued EVAN COOPER
Green Building Final 1/13/2026 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved EVAN COOPER
Service/Power Release 1/13/2026 Approved EVAN COOPER
Smoke Detectors 1/13/2026 Approved EVAN COOPER
Final 1/27/2026 Not Ready for Inspection EVAN COOPER
Final 5/28/2026 Conditional Approval EVAN COOPER
PLUMBING-Final 5/28/2026 Approved EVAN COOPER
Final 6/2/2026 OK to Issue CofO EVAN COOPER