950 N MORAGA DR 90049
Certificate Information: 950 N MORAGA DR 90049
- Application / Permit
- 21010-30000-02981
- Plan Check / Job No.
- B21WL02626
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story s.f.d. *** 1 of 5 ***
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO in Progress on 5/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | TARIK SAOUD |
| Corrections Issued | 7/4/2021 | TARIK SAOUD |
| Quality Review Completed | 7/8/2021 | CHIHARU SUZUKI |
| Plans on Hold | 12/2/2021 | TARIK SAOUD |
| Hold Released | 2/4/2022 | TARIK SAOUD |
| Plans on Hold | 2/4/2022 | TARIK SAOUD |
| Hold Released | 2/9/2022 | CHIHARU SUZUKI |
| Plans on Hold | 2/24/2022 | CHIHARU SUZUKI |
| Hold Released | 4/5/2022 | CHIHARU SUZUKI |
| Plans on Hold | 4/28/2022 | CHIHARU SUZUKI |
| Hold Released | 5/10/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 5/10/2022 | CHIHARU SUZUKI |
| Issued | 5/10/2022 | APPLICANT |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| CofO in Progress | 5/28/2026 | EVAN COOPER |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/24/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/24/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/24/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/24/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 9/24/2021 | DINAH GARIN |
| Permit | Cleared | 9/24/2021 | DINAH GARIN |
| Sewer availability | Cleared | 9/24/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | DINAH GARIN |
| Frnt yard landscape/Water mgmt | Cleared | 10/4/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 12/7/2021 | ROBERT DUFF |
| Trees in Parkway | Cleared | 12/9/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 1/13/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | DINAH GARIN |
| Watercourse | Cleared | 3/9/2022 | TERRY PHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Yadegari,, Shahriar; Lic. No.: C64591 | 10301 KESWICK AVE LOS ANGELES, CA 90064 |
| Engineer | Yazdan,, Fred Faramarz; Lic. No.: C35704 | 58 FEATHER RIDGE MISSION VIEJO, CA 92692 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/5/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 7/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/7/2022 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/14/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Underground Mechanical | 7/14/2022 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Partial Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 9/1/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Approved | CARLOS MATAMOROS |
| Wood Frame | 10/5/2022 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 10/12/2022 | Conditional Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 12/5/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 12/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 12/5/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Approved | CARLOS MATAMOROS |
| Shower Pan | 3/15/2023 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/28/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/28/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 3/28/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 3/28/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/21/2023 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 4/28/2023 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Wood Construction | 5/2/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 5/23/2023 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 5/23/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 5/23/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/23/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/26/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 5/26/2023 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 5/26/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/21/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 6/21/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 6/21/2023 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 6/27/2023 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 7/7/2023 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/10/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 5/10/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/10/2024 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 9/27/2024 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 10/7/2024 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 10/9/2024 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 10/10/2024 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 10/23/2024 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 11/7/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/25/2024 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 11/25/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/30/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/30/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/12/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/12/2025 | Approved | CARLOS MATAMOROS |
| Wood Frame | 2/12/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | STEPHANIE SWANSON |
| Insulation | 2/24/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/24/2025 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 4/11/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 7/30/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 7/30/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 7/30/2025 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 7/30/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 8/7/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 8/7/2025 | Corrections Issued | CARLOS MATAMOROS |
| Service/Power Release | 8/7/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 8/8/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/18/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 8/18/2025 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/16/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 9/16/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 9/16/2025 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Final | 11/5/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 11/5/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 11/5/2025 | Partial Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 11/12/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 11/12/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 11/12/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 11/12/2025 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 11/18/2025 | Conditional Approval | ANDREW NAVE |
| HVAC-Final | 11/18/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 11/18/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 11/24/2025 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 12/3/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 12/3/2025 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 12/3/2025 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 12/15/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/9/2026 | Approved | EVAN COOPER |
| Final | 1/13/2026 | Corrections Issued | EVAN COOPER |
| Green Building Final | 1/13/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/13/2026 | Approved | EVAN COOPER |
| Final | 1/27/2026 | Not Ready for Inspection | EVAN COOPER |
| Final | 5/28/2026 | OK to Issue CofO | EVAN COOPER |