6517-6519 S MENLO AVE 90044

Certificate Information: 6517-6519 S MENLO AVE 90044

Application / Permit
21010-30000-02756
Plan Check / Job No.
B21WL02476
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-Story Duplex B Located at Rear *** 2 of 2 ***
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 2/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 DAVID CASTILLO
Corrections Issued 6/21/2021 DAVID CASTILLO
Quality Review Completed 6/30/2021 TARIK SAOUD
Applicant returned to address corrections 10/13/2021 DAVID CASTILLO
Plan Check Approved 10/19/2021 DAVID CASTILLO
Issued 11/8/2021 APPLICANT
Building Plans Picked Up 11/10/2021 APPLICANT
CofO in Progress 1/30/2023 LILIANA PORTILLO
Permit Finaled 2/2/2023 DEROLD HAUFF
CofO Issued 2/2/2023 DEROLD HAUFF
Permit Finaled 2/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 6/25/2021 STEVE MELGAR
Address approval Cleared 7/1/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/23/2021 STEVE MELGAR
Sewer availability Cleared 7/23/2021 STEVE MELGAR
Trees in Parkway Cleared 9/2/2021 JOHN KIM
Hydrant and Access approval Cleared 9/15/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/27/2021 NICK RAYGOZA
Roof/Waste drainage to street Cleared 9/30/2021 STEVE MELGAR

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 9036 IMPERIAL HWY      DOWNEY, CA 90242
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/19/2021 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 11/19/2021 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 11/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/1/2021 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 12/2/2021 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 12/6/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 3/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 3/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/22/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/26/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 4/26/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 4/26/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 5/4/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/11/2022 Approved LILIANA PORTILLO
Green Building Rough 5/11/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 5/11/2022 Approved LILIANA PORTILLO
Insulation 5/18/2022 Corrections Issued LILIANA PORTILLO
Insulation 5/23/2022 Approved LILIANA PORTILLO
Drywall Nailing 5/27/2022 No Access for Inspection HORACE FULTZ
Interior/Exterior Lathing 5/27/2022 No Access for Inspection HORACE FULTZ
Drywall Nailing 6/2/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/2/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/19/2022 Corrections Issued LILIANA PORTILLO
Final 12/19/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 12/19/2022 Not Ready for Inspection LILIANA PORTILLO
Gas Test 12/19/2022 Approved LILIANA PORTILLO
Green Building Final 12/19/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 12/19/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 12/19/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 12/19/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/19/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/9/2023 Not Ready for Inspection LILIANA PORTILLO
Final 1/9/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 1/9/2023 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 1/9/2023 Not Ready for Inspection LILIANA PORTILLO
Special/Order Compliance 1/11/2023 Partial Approval SABAS ALONSO
ELECTRICAL-Final 1/19/2023 Not Ready for Inspection LILIANA PORTILLO
Final 1/19/2023 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 1/19/2023 Approved LILIANA PORTILLO
Green Building Final 1/19/2023 Approved LILIANA PORTILLO
HVAC-Final 1/19/2023 Approved LILIANA PORTILLO
Service/Power Release 1/19/2023 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 1/26/2023 Approved LILIANA PORTILLO
Final 1/26/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 1/26/2023 Approved LILIANA PORTILLO
Service/Power Release 1/26/2023 Approved LILIANA PORTILLO