1325 1/2 S 6TH AVE 90291
Certificate Information: 1325 1/2 S 6TH AVE 90291
- Application / Permit
- 21010-30000-02709
- Plan Check / Job No.
- B21WL02418
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single story SFD (442 sf) at rear of the lot. All work per DIR-2018-43-CDP-MEL
- Permit Issued
- Issued on 12/8/2022
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 12/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/28/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 7/8/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/12/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 7/25/2022 | APPLICANT |
| Applicant returned to address corrections | 12/1/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 12/7/2022 | REZA HAGHIGHAT |
| Issued | 12/8/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/2/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 10/8/2021 | GILBERT URREA |
| Specific Plan | Cleared | 3/31/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 4/4/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | DINAH GARIN |
| ZA Case | Cleared | 9/8/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 9/8/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 9/22/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 9/22/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 9/22/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 9/22/2022 | BRENNEN OBETO |
| Coastal Zone | Cleared | 9/27/2022 | BRENNEN OBETO |
| Specific Plan | Cleared | 9/27/2022 | BRENNEN OBETO |
| ZI | Cleared | 9/27/2022 | BRENNEN OBETO |
Contact Information
| Architect | Vitalich,, Stephen Anthony; Lic. No.: C19742 | 558 SAN JUAN AVENUE VENICE, CA 90291 |
| Contractor | Owner-Builder | , |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Barrier | 12/27/2022 | Approved | EVAN COOPER |
| METHANE-Rough | 12/27/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 12/27/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 12/27/2022 | No Access for Inspection | EVAN COOPER |
| Pre-Inspection | 2/2/2023 | Partial Inspection | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 2/13/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 3/1/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 3/1/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Approved | EVAN COOPER |
| Green Building Rough | 3/1/2023 | Approved | EVAN COOPER |
| Grounding or Bonding | 3/1/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 3/1/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/1/2023 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/1/2023 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 3/10/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 3/10/2023 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 3/10/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/14/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/22/2023 | Approved | EVAN COOPER |
| Insulation | 3/22/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/6/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/8/2023 | Approved | EVAN COOPER |
| Final | 6/8/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/8/2023 | Conditional Approval | EVAN COOPER |
| Gas Test | 6/8/2023 | Approved | EVAN COOPER |
| HVAC-Final | 6/8/2023 | Approved | EVAN COOPER |
| METHANE-Subgrade | 6/8/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/8/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/8/2023 | Approved | EVAN COOPER |