837 N HAVERFORD AVE 90272
Certificate Information: 837 N HAVERFORD AVE 90272
- Application / Permit
- 21010-30000-02664
- Plan Check / Job No.
- B21WL02351
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story house w/ roof trusses
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 6/22/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 7/1/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/15/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 11/10/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 11/12/2021 | FELIPE HERNANDEZ |
| Issued | 11/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| CofO in Progress | 12/6/2022 | BRENDAN LOONEY |
| Permit Finaled | 2/2/2023 | DANIEL ORRANTE |
| CofO Issued | 2/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/24/2021 | LOUIS ORTEGA |
| Permit | Cleared | 6/27/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/28/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 9/10/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/8/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/12/2021 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 11/10/2021 | FELIPE HERNANDEZ |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/22/2022 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 3/30/2022 | Approved | ANDREW NAVE |
| Deputy Wood Construction | 4/13/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 5/5/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 5/31/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 6/2/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 6/2/2022 | Not Ready for Inspection | ANDREW NAVE |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/7/2022 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 6/9/2022 | Approved | ANDREW NAVE |
| Shower Pan | 6/9/2022 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 6/14/2022 | Approved | ANDREW NAVE |
| Shower Pan | 6/14/2022 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 6/14/2022 | Approved | ANDREW NAVE |
| Insulation | 6/17/2022 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 6/30/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 6/30/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 10/3/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 10/12/2022 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Final | 10/18/2022 | Conditional Approval | BRENDAN LOONEY |
| Gas Test | 10/18/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 10/18/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 10/26/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 10/26/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 11/17/2022 | Approved | BRENDAN LOONEY |
| Final | 12/2/2022 | OK to Issue CofO | BRENDAN LOONEY |
| Green Building Final | 12/2/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 12/2/2022 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 12/2/2022 | Approved | BRENDAN LOONEY |