3137 S CURTS AVE 90034
Certificate Information: 3137 S CURTS AVE 90034
- Application / Permit
- 21010-30000-02662
- Plan Check / Job No.
- B21WL02350
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD (2,355 sf) w./ att. 2-car garage (314 sf) at front of the lot
- Permit Issued
- Issued on 1/31/2022
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/21/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 6/30/2021 | TARIK SAOUD |
| Plan Check Approved | 12/29/2021 | REZA HAGHIGHAT |
| Issued | 1/31/2022 | APPLICANT |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| CofO in Progress | 2/20/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
| CofO Issued | 2/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/28/2021 | MOHAMMAD HASAN |
| Specific Plan | Cleared | 6/28/2021 | MOHAMMAD HASAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 7/29/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | JEANIE LAM |
| Address approval | Cleared | 8/11/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/23/2021 | JEANIE LAM |
| Specific Plan | Cleared | 8/31/2021 | DYLAN SITTIG |
| Hydrant and Access approval | Cleared | 9/13/2021 | MATTHEW CRAIG |
| Community Plan Implem. Overlay | Cleared | 10/5/2021 | KYLE WINSTON |
| Miscellaneous | Cleared | 10/5/2021 | KYLE WINSTON |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Powers Dave Construction; Lic. No.: 902159-B | 75 MALAGA COVE PLAZA #14 PALOS VERDES ESTATES, CA 90274 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/26/2022 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/13/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/18/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/30/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 10/31/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/2/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 11/2/2022 | Not Ready for Inspection | EVAN COOPER |
| MERV13>=Rough | 11/2/2022 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 11/2/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 11/7/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 11/22/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | MICHAEL PELHAM |
| Shower Pan | 11/22/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 11/22/2022 | Partial Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | CLAYTON GRAHAM |
| Insulation | 12/27/2022 | Approved | JEREMY TODD |
| Special/Order Compliance | 12/27/2022 | Partial Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 1/4/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 1/30/2023 | Conditional Approval | JEREMY TODD |
| Green Building Rough | 1/30/2023 | Conditional Approval | JEREMY TODD |
| Underground Mechanical | 7/17/2023 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 7/21/2023 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 7/21/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 9/13/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 9/28/2023 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 10/12/2023 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Final | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 11/2/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Final | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| MERV13>=Final | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| MERV13>=Rough | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 11/9/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Smoke Detectors | 11/9/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Final | 11/30/2023 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Final | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| MERV13>=Final | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| MERV13>=Rough | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Final | 2/14/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| Service/Power Release | 2/20/2024 | Approved | MEL KHACHATOURIAN |