440 E 90TH ST 90003
Certificate Information: 440 E 90TH ST 90003
- Application / Permit
- 21010-30000-02631
- Plan Check / Job No.
- B21WL02309
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New two story ADU *** 2 of 2 ***
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | RICHARD GARCIA |
| Corrections Issued | 6/18/2021 | RICHARD GARCIA |
| Quality Review Completed | 6/28/2021 | TARIK SAOUD |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| Applicant returned to address corrections | 12/21/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 1/25/2022 | RICHARD GARCIA |
| Plan Check Approved | 2/17/2022 | RICHARD GARCIA |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 12/21/2022 | LILIANA PORTILLO |
| CofO Issued | 1/18/2023 | DEROLD HAUFF |
| Permit Finaled | 1/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | CHINH DINH |
| Sewer availability | Cleared | 9/14/2021 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 10/8/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/5/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 11/12/2021 | JEANETTE VONG |
| Green Code | Cleared | 2/17/2022 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 3/31/2022 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/10/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 6/10/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 7/14/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/26/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/1/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/1/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/1/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/10/2022 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 8/10/2022 | Approved | RYAN SALAZAR |
| Insulation | 8/22/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/30/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/30/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 11/10/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 11/10/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 11/10/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/5/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 12/5/2022 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 12/5/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 12/5/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 12/5/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/5/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 12/5/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 12/5/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/9/2022 | Conditional Approval | LILIANA PORTILLO |
| Final | 12/9/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Gas Test | 12/9/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 12/9/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/20/2022 | Approved | LILIANA PORTILLO |
| Final | 12/20/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 12/20/2022 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 12/20/2022 | Approved | LILIANA PORTILLO |