4430-4432 W CAMERO AVE 90027
Certificate Information: 4430-4432 W CAMERO AVE 90027
- Application / Permit
- 21010-30000-02597
- Plan Check / Job No.
- B21WL02262
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (n) 2-family dwelling, both w/ 2 (n) car garage and roof trusses
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 6/14/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 6/25/2021 | TARIK SAOUD |
| Plan Check Approved | 9/29/2021 | FELIPE HERNANDEZ |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 11/16/2022 | JOSEPH MCGARRY |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
| CofO Issued | 12/10/2022 | DEROLD HAUFF |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 8/9/2021 | JOHN KIM |
| Address approval | Cleared | 8/25/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2021 | JEANIE LAM |
| Permit | Cleared | 8/25/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/25/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/10/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/15/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 9/21/2021 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 9/29/2021 | FELIPE HERNANDEZ |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/29/2021 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 11/29/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 11/29/2021 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/17/2021 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/25/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/1/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 3/14/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 3/14/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 3/15/2022 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 3/16/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 3/21/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/29/2022 | No Access for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/1/2022 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 4/1/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/1/2022 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 4/1/2022 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 4/1/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 4/11/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 4/18/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 4/20/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/20/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 8/1/2022 | No Access for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | JOSEPH MCGARRY |
| Final | 8/2/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/2/2022 | Approved | JOSEPH MCGARRY |
| Gas Test | 8/2/2022 | Approved | JOSEPH MCGARRY |
| Green Building Final | 8/2/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 8/2/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 8/2/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 8/15/2022 | No Access for Inspection | JOSEPH MCGARRY |
| PLUMBING-Final | 8/18/2022 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 8/23/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Final | 8/23/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 8/23/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 11/1/2022 | Approved | JOSEPH MCGARRY |
| Final | 11/1/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 11/1/2022 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 11/1/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 11/8/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 11/8/2022 | Approved | JOSEPH MCGARRY |
| Final | 11/15/2022 | OK to Issue CofO | JOSEPH MCGARRY |