755 N ALFRED ST 1-5 90069
Certificate Information: 755 N ALFRED ST 1-5 90069
- Application / Permit
- 21010-30000-02504
- Plan Check / Job No.
- B21WL02210
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 5-single family dwellings attached with common walls (TOWNHOUSES) WITH ATTACHED GARAGES
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | TARIK SAOUD |
| Corrections Issued | 6/15/2021 | TARIK SAOUD |
| Quality Review Completed | 6/22/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 7/18/2022 | TARIK SAOUD |
| Plan Check Approved | 7/22/2022 | TARIK SAOUD |
| Issued | 8/1/2022 | APPLICANT |
| Building Plans Picked Up | 8/1/2022 | APPLICANT |
| TCO Issued (Expire Date: 05-11-2025) | 11/12/2024 | ADAM BURGESS |
| Permit Finaled | 1/28/2025 | RAFAEL ESPINOZA |
| CofO Issued | 1/28/2025 | RAFAEL ESPINOZA |
| Permit Finaled | 1/28/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/18/2021 | RIDWAN HARDY |
| Address approval | Cleared | 11/23/2021 | CINDY QI |
| Permit | Cleared | 11/23/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | CINDY QI |
| Sewer availability | Cleared | 11/24/2021 | CINDY QI |
| Hydrant and Access approval | Cleared | 1/8/2022 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/11/2022 | SUNG JOON WON |
| "Q" conditions | Cleared | 3/14/2022 | ANNA VIDAL |
| Frnt yard landscape/Water mgmt | Cleared | 3/14/2022 | ANNA VIDAL |
| Roof/Waste drainage to street | Cleared | 3/16/2022 | AMAAN MALIK |
| Trees in Parkway | Cleared | 4/19/2022 | TARIK SAOUD |
| Green Code | Cleared | 5/19/2022 | AARON COSTA |
| DAS Clearance | Cleared | 5/25/2022 | TARIK SAOUD |
| Building over 36-ft | Cleared | 7/18/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Fronen Construction Inc; Lic. No.: 1053555-B | 12400 VENTURA BLVD #336 STUDIO CITY, CA 91604 |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 11/1/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/15/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 3/7/2023 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/24/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 4/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 4/26/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 4/28/2023 | Conditional Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 5/16/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Wood Construction | 6/6/2023 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 6/30/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Rough | 11/27/2023 | Partial Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 11/27/2023 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 11/27/2023 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 12/6/2023 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 12/6/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 12/6/2023 | Corrections Issued | EDWIN GREGORYONA |
| Deputy Wood Construction | 2/7/2024 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 2/7/2024 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 3/4/2024 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 3/4/2024 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 3/7/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 3/18/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 3/26/2024 | Approved | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 3/26/2024 | Approved | RAMAZANALI ALMASI |
| Pre-Inspection | 9/4/2024 | Approved | EDWIN GREGORYONA |
| Final | 10/23/2024 | Conditional Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 10/23/2024 | Approved | EDWIN GREGORYONA |
| Green Building Final | 10/23/2024 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 10/23/2024 | Approved | EDWIN GREGORYONA |
| Wood Frame | 10/23/2024 | Approved | EDWIN GREGORYONA |