10528 W ROUNTREE ROAD 90064
Certificate Information: 10528 W ROUNTREE ROAD 90064
- Application / Permit
- 21010-30000-02367
- Plan Check / Job No.
- B21WL02022
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 story house w/ basement. Equipped with an automatic residential fire sprinkler system in accordance with section R313.3 or NFPA13D.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | ALFREDO JARA |
| Corrections Issued | 6/3/2021 | ALFREDO JARA |
| Quality Review Completed | 6/14/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 8/9/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 8/27/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 9/1/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/18/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 11/22/2021 | ALFREDO JARA |
| Plan Check Approved | 12/17/2021 | ALFREDO JARA |
| Issued | 12/22/2021 | APPLICANT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Permit Finaled | 1/16/2025 | RICHARD STEINBACH |
| CofO Issued | 1/16/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/16/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/30/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 9/19/2021 | JOHN CONNEALLY |
| Specific Plan | Cleared | 10/7/2021 | VALERIA CEJA |
| Low Impact Development | Cleared | 10/27/2021 | ANTHONY VARGAS |
| Trees in Parkway | Cleared | 10/28/2021 | ADALBERTO VERA |
| Permit | Cleared | 11/1/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/1/2021 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 11/22/2021 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 11/22/2021 | ALFREDO JARA |
| Excavation more than 5-ft deep | Cleared | 12/17/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Jensen C A Construction; Lic. No.: 437501-B | 8961 GLADBECK AVE NORTHRIDGE, CA 91324 |
| Engineer | Coffey,, Trisha A; Lic. No.: C67657 | 360 MILLER WAY ARROYO GRANDE, CA 93420 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/25/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/8/2022 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 4/8/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/21/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/25/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/25/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 5/18/2022 | Conditional Approval | KEVIN SARGSYAN |
| Underground Mechanical | 6/27/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/13/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/12/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 10/5/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 1/24/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Deputy Wood Construction | 1/26/2023 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 4/11/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 4/11/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 4/11/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Wood Frame | 4/11/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 5/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Partial Approval | CLAYTON GRAHAM |
| Drywall Nailing | 5/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/31/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 6/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 6/14/2023 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 6/14/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 6/21/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 7/7/2023 | Partial Approval | CLAYTON GRAHAM |
| HVAC-Rough | 7/7/2023 | Approved | CLAYTON GRAHAM |
| Gas Test | 7/10/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/10/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 7/10/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 7/13/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 7/13/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 8/9/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | CLAYTON GRAHAM |
| Special/Order Compliance | 8/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Final | 8/11/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/11/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 9/1/2023 | Corrections Issued | CLAYTON GRAHAM |
| Drywall Nailing | 9/18/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 10/4/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/4/2023 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 10/4/2023 | Partial Approval | BEN MOLSTAD |
| Sewer | 12/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 12/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/2/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Gas Test | 2/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 2/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 3/8/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/2/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/16/2024 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 7/16/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Gas Test | 7/19/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Service/Power Release | 7/19/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Gas Test | 7/24/2024 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 7/24/2024 | Corrections Issued | ASHLEY THOMPSON |
| Service/Power Release | 7/24/2024 | Approved | KENNETH NAGLE |
| Gas Test | 8/20/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 8/20/2024 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/10/2024 | Approved | ASHLEY THOMPSON |
| Final | 10/10/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 10/10/2024 | Approved | ASHLEY THOMPSON |
| Green Building Final | 10/10/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 10/10/2024 | Approved | ASHLEY THOMPSON |
| Reinforced Concrete Frame | 10/10/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Not Ready | ASHLEY THOMPSON |
| Service/Power Release | 10/10/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 10/10/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 12/23/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 12/23/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 12/23/2024 | Approved | CHRISTOPHER WILSON |
| Final | 12/31/2024 | Corrections Issued | KIRK SANDERS |
| Final | 1/6/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 1/15/2025 | Conditional Approval | ASHLEY THOMPSON |