5232-5232 1/2 N TILDEN AVE 91401
Certificate Information: 5232-5232 1/2 N TILDEN AVE 91401
- Application / Permit
- 21010-30000-02264
- Plan Check / Job No.
- B21WL01936
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 3-story SFD w/ attached 3-story ADU (rear)
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 6/1/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 6/11/2021 | TARIK SAOUD |
| Plan Check Approved | 10/6/2021 | FELIPE HERNANDEZ |
| Issued | 11/10/2021 | APPLICANT |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| CofO in Progress | 10/4/2022 | RICHARD DOCKUS |
| CofO Issued | 11/2/2022 | MICHAEL SMITH |
| Permit Finaled | 11/2/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | ADRIAN CASTRO |
| Highway dedication | Cleared | 6/15/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/15/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 8/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/14/2021 | ABDULLAH SADOZAI |
| Hydrant and Access approval | Cleared | 9/9/2021 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 10/1/2021 | LOUIS ORTEGA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/8/2021 | Approved | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 12/22/2021 | Corrections Issued | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 12/27/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/27/2021 | Corrections Issued | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 2/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 2/7/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/14/2022 | Approved | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Partial Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 5/6/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 5/6/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/10/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 5/12/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/16/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 5/27/2022 | Conditional Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/2/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/2/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/2/2022 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 6/2/2022 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 6/2/2022 | Approved | RICHARD DOCKUS |
| Insulation | 6/8/2022 | Approved | MATT KELLERMAN |
| Drywall Nailing | 6/14/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/14/2022 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/22/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 9/13/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 9/14/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 9/19/2022 | Approved | RICHARD DOCKUS |
| Final | 9/27/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Gas Test | 9/27/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Final | 9/27/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Final | 9/27/2022 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | DEANDRE HOFFMAN |
| Service/Power Release | 9/27/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Smoke Detectors | 9/27/2022 | Approved | DEANDRE HOFFMAN |
| Final | 10/3/2022 | OK to Issue CofO | RICHARD DOCKUS |
| HVAC-Final | 10/3/2022 | Approved | RICHARD DOCKUS |
| Service/Power Release | 10/3/2022 | Approved | RICHARD DOCKUS |