12630 W SUNSET BLVD 90049

Certificate Information: 12630 W SUNSET BLVD 90049

Application / Permit
21010-30000-02261
Plan Check / Job No.
B21WL01928
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 1-story ADU per CA Govt Code 65852.2(e)(1)(B) and applicable par of LAMC 12.22 A.33 (c)-(d),(g)
Permit Issued
Issued on 8/16/2022
Issuing Office
Current Status
CofO Issued on 2/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 FELIPE HERNANDEZ
Corrections Issued 5/27/2021 FELIPE HERNANDEZ
Quality Review Completed 6/8/2021 TARIK SAOUD
Applicant returned to address corrections 12/14/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 7/11/2022 FELIPE HERNANDEZ
Plan Check Approved 8/13/2022 FELIPE HERNANDEZ
Issued 8/16/2022 APPLICANT
Building Plans Picked Up 8/17/2022 APPLICANT
Permit Finaled 2/9/2026 CLAUDIO MORENO
CofO Issued 2/9/2026 CLAUDIO MORENO
Permit Finaled 2/9/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 6/18/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/22/2021 DINAH GARIN
Sewer availability Cleared 6/22/2021 DINAH GARIN
Specific Plan Cleared 8/3/2021 VALERIA CEJA
Hydrant and Access approval Cleared 9/25/2021 RUEL COLE
Low Impact Development Cleared 3/9/2022 TA ANH
Roof/Waste drainage to street Cleared 4/14/2022 JENSON LEE
Watercourse Cleared 6/15/2022 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 8/13/2022 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 8/13/2022 FELIPE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2022 Approved RYAN BARNES
Footing/Foundation/Slab 3/1/2023 Corrections Issued RYAN BARNES
Wood Frame 3/1/2023 Not Ready for Inspection RYAN BARNES
BUILDING-Rough-Frame 4/13/2023 Not Ready for Inspection RYAN BARNES
FLOOD-Proofing Certificate 4/13/2023 Not Ready for Inspection RYAN BARNES
Green Building Rough 4/13/2023 Approved RYAN BARNES
Verify Sprinkler Sign Off 4/13/2023 Not Ready for Inspection RYAN BARNES
BUILDING-Rough-Frame 4/25/2023 Conditional Approval RYAN BARNES
Deck 4/25/2023 Approved RYAN BARNES
FLOOD-Proofing Certificate 4/25/2023 Approved RYAN BARNES
Footing/Foundation/Slab 4/25/2023 Approved RYAN BARNES
Verify Sprinkler Sign Off 4/25/2023 Approved RYAN BARNES
Wood Frame 4/25/2023 Conditional Approval RYAN BARNES
PLUMBING-Rough 5/3/2023 Partial Approval RYAN BARNES
ELECTRICAL-Rough 5/15/2023 Partial Approval RYAN BARNES
ELECTRICAL-Rough 6/5/2023 Approved RYAN BARNES
HVAC-Rough 6/5/2023 Approved RYAN BARNES
PLUMBING-Rough 6/5/2023 Corrections Issued RYAN BARNES
PLUMBING-Rough 6/30/2023 Not Ready for Inspection ANDREW BEELI
Sewer 6/30/2023 Corrections Issued ANDREW BEELI
PLUMBING-Rough 7/6/2023 Approved JOHN MATTILLO
Insulation 7/11/2023 Approved JOHN MATTILLO
Drywall Nailing 8/3/2023 Corrections Issued JEREMY TODD
Interior/Exterior Lathing 8/10/2023 Approved JEREMY TODD
Shower Pan 8/10/2023 Approved JEREMY TODD
Interior/Exterior Lathing 10/11/2023 Approved RYAN BARNES
ELECTRICAL-Final 4/25/2024 Corrections Issued RYAN BARNES
HVAC-Final 4/25/2024 Corrections Issued RYAN BARNES
PLUMBING-Final 4/25/2024 Approved RYAN BARNES
Smoke Detectors 4/25/2024 Approved RYAN BARNES
BUILDING-Rough-Frame 5/7/2024 Approved RYAN BARNES
Drywall Nailing 5/7/2024 Approved RYAN BARNES
ELECTRICAL-Final 5/7/2024 Approved RYAN BARNES
Final 5/7/2024 Conditional Approval RYAN BARNES
Green Building Final 5/7/2024 Approved RYAN BARNES
HVAC-Final 5/7/2024 Approved RYAN BARNES
PLUMBING-Final 5/7/2024 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 5/7/2024 SGSOV Approved RYAN BARNES