1758 W 39TH ST 90062
Certificate Information: 1758 W 39TH ST 90062
- Application / Permit
- 21010-30000-02184
- Plan Check / Job No.
- B21WL01890
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 10/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2021 | RICHARD GARCIA |
| Corrections Issued | 5/8/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/19/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/30/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 12/23/2021 | JASON JANGADA |
| Applicant returned to address corrections | 1/15/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/7/2022 | RICHARD GARCIA |
| Plan Check Approved | 2/17/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 2/24/2022 | APPLICANT |
| Issued | 3/15/2022 | APPLICANT |
| CofO in Progress | 7/21/2023 | STUART CHAPMAN |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
| CofO Issued | 10/9/2023 | DEROLD HAUFF |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2021 | WALLIE JONG |
| Sewer availability | Cleared | 6/2/2021 | WALLIE JONG |
| Address approval | Cleared | 6/7/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/19/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 10/13/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/16/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/17/2022 | Approved | SABAS ALONSO |
| Sewer | 10/17/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Not Ready | HORACE FULTZ |
| BUILDING-Rough-Frame | 11/22/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 11/22/2022 | Approved | SABAS ALONSO |
| Insulation | 12/1/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 12/1/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/26/2023 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 1/26/2023 | Partial Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 1/26/2023 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 2/17/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 2/17/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 2/17/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/17/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/17/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 2/17/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/2/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 3/8/2023 | Conditional Approval | SABAS ALONSO |
| Insulation | 3/17/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 3/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/30/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 4/5/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/9/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 5/9/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 5/9/2023 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 5/9/2023 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Final | 5/9/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 5/9/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 5/9/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 6/23/2023 | Approved | SABAS ALONSO |
| Final | 6/23/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/23/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 6/23/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/23/2023 | Approved | SABAS ALONSO |
| Final | 7/5/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 7/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/17/2023 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 7/17/2023 | Approved | STUART CHAPMAN |