2225 S GLYNDON AVE 90291

Certificate Information: 2225 S GLYNDON AVE 90291

Application / Permit
21010-30000-02145
Plan Check / Job No.
B21WL01839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 story addition w/attached garage to (E) 1 story SFD. Only small portion of foundation to remain
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 7/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2021 APPLICANT
Assigned to Plan Check Engineer 5/12/2021 FELIPE HERNANDEZ
Corrections Issued 5/17/2021 FELIPE HERNANDEZ
Quality Review Completed 6/1/2021 TARIK SAOUD
Plan Check Approved 8/30/2021 FELIPE HERNANDEZ
Issued 9/23/2021 APPLICANT
CofO in Progress 7/20/2022 DAVID FEILER
Permit Finaled 7/25/2022 DANIEL ORRANTE
CofO Issued 7/25/2022 DANIEL ORRANTE
Permit Finaled 7/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 6/4/2021 NOAH MCCOY
Hydrant and Access approval Cleared 6/9/2021 JOHN CONNEALLY
Low Impact Development Cleared 8/4/2021 SUNG JOON WON
Permit Cleared 8/6/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/10/2021 CATHERINE ADROVER
Sewer availability Cleared 8/10/2021 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 8/12/2021 CATHERINE ADROVER
Specific Plan Cleared 8/17/2021 KEVIN ARUCAN
Trees in Parkway Cleared 8/25/2021 JOHN KIM

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2021 Not Ready for Inspection DAVID FEILER
Pre-Inspection 10/18/2021 Partial Inspection DAVID FEILER
PLUMBING-Rough 10/29/2021 Partial Approval DAVID FEILER
Sewer 10/29/2021 Approved DAVID FEILER
Excavation/Setback/Form/Re-Bar 11/9/2021 Approved DAVID FEILER
Footing/Foundation/Slab 11/9/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 12/17/2021 Conditional Approval DAVID FEILER
Deputy Drilled-In Anchors 12/27/2021 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/6/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Inspection DAVID FEILER
HVAC-Rough 1/6/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 1/20/2022 Approved DAVID FEILER
HVAC-Rough 1/20/2022 Approved DAVID FEILER
PLUMBING-Rough 1/20/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 2/1/2022 Conditional Approval DAVID FEILER
Green Building Rough 2/1/2022 Approved DAVID FEILER
Insulation 2/1/2022 Approved DAVID FEILER
Shower Pan 2/1/2022 Approved DAVID FEILER
Verify Sprinkler Sign Off 2/1/2022 Approved DAVID FEILER
Drywall Nailing 2/14/2022 Approved DAVID FEILER
Interior/Exterior Lathing 2/14/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 2/17/2022 Approved DAVID FEILER
Interior/Exterior Lathing 2/17/2022 Approved DAVID FEILER
PLUMBING-Final 5/18/2022 Corrections Issued JESUS RODRIGUEZ
Verify Rec and Parks Fee Memo 5/18/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Final 5/26/2022 Approved JESUS RODRIGUEZ
Gas Test 5/26/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/26/2022 Approved JESUS RODRIGUEZ
Final 6/14/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/14/2022 Approved JESUS RODRIGUEZ
HVAC-Final 6/14/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 6/14/2022 Approved JESUS RODRIGUEZ
Final 6/22/2022 Corrections Issued DAVID FEILER
HVAC-Final 6/22/2022 Corrections Issued DAVID FEILER
Final 7/13/2022 Conditional Approval DAVID FEILER
Service/Power Release 7/13/2022 Approved DAVID FEILER
Final 7/20/2022 OK to Issue CofO DAVID FEILER
HVAC-Final 7/20/2022 Approved DAVID FEILER