13739 1/2 W LOUVRE ST 91331

Certificate Information: 13739 1/2 W LOUVRE ST 91331

Application / Permit
21010-30000-01890
Plan Check / Job No.
B21WL01674
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) and WFPP
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 9/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2021 APPLICANT
Assigned to Plan Check Engineer 4/28/2021 JASON JANGADA
Corrections Issued 4/29/2021 JASON JANGADA
Applicant returned to address corrections 9/30/2021 KAVIAN REFAHI
Plan Check Approved 9/30/2021 KAVIAN REFAHI
Issued 12/1/2021 APPLICANT
Building Plans Picked Up 12/3/2021 APPLICANT
CofO in Progress 8/11/2023 MICHEL ABAJAN
CofO Issued 9/19/2023 RUBEN SALAS
Permit Finaled 9/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/7/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/17/2021 ADRIAN CASTRO
Sewer availability Cleared 5/17/2021 ADRIAN CASTRO
Clean Up Green Up Cleared 5/18/2021 RUBEN VASQUEZ
ZA Case Cleared 5/18/2021 RUBEN VASQUEZ
ZI Cleared 5/18/2021 RUBEN VASQUEZ
Hydrant and Access approval Cleared 6/30/2021 KURT CORRAL
Low Impact Development Cleared 8/26/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/2/2021 DAGOVERTO GUERRERO

Contact Information

Contractor C S W F Construction Inc; Lic. No.: 1021458-B 625 N UNRUH AVE # 2      LA PUENTE, CA 91744

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/21/2021 Corrections Issued JOHN HAYES
METHANE-Barrier 12/21/2021 Not Ready for Inspection JOHN HAYES
METHANE-Subgrade 12/21/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 1/13/2022 Approved MICHEL ABAJAN
METHANE-Barrier 1/13/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 1/13/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 1/25/2022 Approved MICHEL ABAJAN
Wood Frame 1/25/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 2/25/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/11/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/11/2022 Approved MICHEL ABAJAN
Green Building Rough 3/11/2022 Approved MICHEL ABAJAN
HVAC-Rough 3/11/2022 Approved MICHEL ABAJAN
METHANE-Rough 3/11/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 3/11/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 3/11/2022 Approved MICHEL ABAJAN
Insulation 3/18/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/18/2022 Approved MICHEL ABAJAN
Drywall Nailing 3/24/2022 Approved MICHEL ABAJAN
Underground Mechanical 7/20/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 8/4/2022 Partial Approval MICHEL ABAJAN
Sewer 9/14/2022 Approved MICHEL ABAJAN
Final 6/13/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 6/13/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 6/13/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 6/13/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 7/19/2023 Corrections Issued MICHEL ABAJAN
Final 7/19/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 7/19/2023 Approved MICHEL ABAJAN
HVAC-Final 7/19/2023 Approved MICHEL ABAJAN
PLUMBING-Final 7/19/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 7/19/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/19/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/11/2023 Approved MICHEL ABAJAN
Final 8/11/2023 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 8/11/2023 Approved MICHEL ABAJAN