13739 1/2 W LOUVRE ST 91331
Certificate Information: 13739 1/2 W LOUVRE ST 91331
- Application / Permit
- 21010-30000-01890
- Plan Check / Job No.
- B21WL01674
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) and WFPP
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2021 | JASON JANGADA |
| Corrections Issued | 4/29/2021 | JASON JANGADA |
| Applicant returned to address corrections | 9/30/2021 | KAVIAN REFAHI |
| Plan Check Approved | 9/30/2021 | KAVIAN REFAHI |
| Issued | 12/1/2021 | APPLICANT |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| CofO in Progress | 8/11/2023 | MICHEL ABAJAN |
| CofO Issued | 9/19/2023 | RUBEN SALAS |
| Permit Finaled | 9/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/17/2021 | ADRIAN CASTRO |
| Clean Up Green Up | Cleared | 5/18/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 5/18/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 5/18/2021 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 6/30/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 8/26/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/2/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 625 N UNRUH AVE # 2 LA PUENTE, CA 91744 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/21/2021 | Corrections Issued | JOHN HAYES |
| METHANE-Barrier | 12/21/2021 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Subgrade | 12/21/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/13/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/13/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/13/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/25/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 1/25/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/25/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/11/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/11/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/11/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 3/11/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/11/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/11/2022 | Approved | MICHEL ABAJAN |
| Insulation | 3/18/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/18/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/24/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 7/20/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 8/4/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 9/14/2022 | Approved | MICHEL ABAJAN |
| Final | 6/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 6/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/13/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/19/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 7/19/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/19/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/19/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/19/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 7/19/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 8/11/2023 | Approved | MICHEL ABAJAN |
| Final | 8/11/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 8/11/2023 | Approved | MICHEL ABAJAN |