751 N SWARTHMORE AVE 90272
Certificate Information: 751 N SWARTHMORE AVE 90272
- Application / Permit
- 21010-30000-01888
- Plan Check / Job No.
- B21WL01665
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-Story S.F.D w/attached Garage, Basement and Roof Deck
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | DAVID CASTILLO |
| Corrections Issued | 5/4/2021 | DAVID CASTILLO |
| Quality Review Completed | 5/10/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 6/29/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/28/2021 | DAVID CASTILLO |
| Plan Check Approved | 10/14/2021 | DAVID CASTILLO |
| Issued | 10/19/2021 | APPLICANT |
| CofO in Progress | 8/18/2023 | KENNETH NAGLE |
| Permit Finaled | 8/23/2023 | DANIEL ORRANTE |
| CofO Issued | 8/23/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 6/11/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 6/29/2021 | DAVID CASTILLO |
| Permit | Cleared | 6/29/2021 | NIKTA MOUSAVI |
| Trees in Parkway | Cleared | 7/1/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 7/19/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 7/28/2021 | DAVID CASTILLO |
| Low Impact Development | Cleared | 9/16/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | NIKTA MOUSAVI |
Contact Information
| Architect | Carolyn, Gibbs Architect; Lic. No.: BUS10862 | 3763 MILLER WAY SACRAMENTO, CA 95817 |
| Contractor | Sowa Development Inc; Lic. No.: 961853-B | 2629 33RD STREET SANTA MONICA, CA 90405 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2022 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 3/23/2022 | Partial Approval | ANDREW NAVE |
| Grounding or Bonding | 3/23/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/25/2022 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 5/5/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/2/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 6/6/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/14/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/17/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 6/23/2022 | Conditional Approval | ANDREW NAVE |
| Deputy Wood Construction | 7/7/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | BRENDAN LOONEY |
| Gas Test | 8/30/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/30/2022 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/2/2022 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 9/7/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | BRENDAN LOONEY |
| Shower Pan | 10/4/2022 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 10/5/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/6/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/12/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 10/12/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/12/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 10/12/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 10/12/2022 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 10/12/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 10/20/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | JUAN VALENZUELA |
| Insulation | 10/28/2022 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 11/10/2022 | Conditional Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/16/2022 | Approved | KENNETH NAGLE |
| Gas Test | 2/1/2023 | Approved | BRENDAN LOONEY |
| Sewer | 2/1/2023 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 2/1/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 6/16/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 6/21/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 6/21/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 6/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 6/27/2023 | Approved | KENNETH NAGLE |
| HVAC-Final | 6/28/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 7/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 8/2/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/2/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 8/2/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 8/2/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 8/2/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/10/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |