8521 W AIRDROME ST 90035

Certificate Information: 8521 W AIRDROME ST 90035

Application / Permit
21010-30000-01840
Plan Check / Job No.
B21WL01137
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 2-CAR GARAGE
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
CofO Issued on 10/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 TARIK SAOUD
Corrections Issued 4/13/2021 TARIK SAOUD
Quality Review Completed 4/23/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/1/2021 VLADIMIR ARUTYUNYAN
Issued 8/6/2021 APPLICANT
CofO in Progress 9/29/2022 EVAN COOPER
Permit Finaled 10/4/2022 DANIEL ORRANTE
CofO Issued 10/4/2022 DANIEL ORRANTE
Permit Finaled 10/4/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/15/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/29/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/15/2021 RENZ SORIANO

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2022 Approved EVAN COOPER
Footing/Foundation/Slab 3/4/2022 Approved EVAN COOPER
METHANE-Barrier 3/4/2022 Approved EVAN COOPER
METHANE-Subgrade 3/4/2022 Approved EVAN COOPER
Wood Frame 3/31/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Partial Approval EVAN COOPER
Wood Frame 5/2/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 5/13/2022 Approved EVAN COOPER
ELECTRICAL-Rough 5/13/2022 Approved EVAN COOPER
Green Building Rough 5/13/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/13/2022 Approved EVAN COOPER
METHANE-Rough 5/13/2022 Approved EVAN COOPER
Drywall Nailing 5/19/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 6/15/2022 Approved EVAN COOPER
Final 6/15/2022 Corrections Issued EVAN COOPER
Green Building Final 6/15/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved EVAN COOPER
Service/Power Release 6/15/2022 Approved EVAN COOPER
Smoke Detectors 6/15/2022 Approved EVAN COOPER
Final 7/8/2022 Not Ready for Inspection EVAN COOPER
HVAC-Final 7/8/2022 Approved EVAN COOPER
PLUMBING-Final 7/8/2022 Approved EVAN COOPER
Final 7/18/2022 Not Ready for Inspection EVAN COOPER
Final 9/19/2022 Not Ready for Inspection ANDREW NAVE
Final 9/28/2022 OK to Issue CofO EVAN COOPER