629 N HARPER AVE 90048

Certificate Information: 629 N HARPER AVE 90048

Application / Permit
21010-30000-01736
Plan Check / Job No.
B21WL01557
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New detached 2 car garage
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/12/2021 MARJAN SHENASI
Corrections Issued 4/13/2021 MARJAN SHENASI
Plan Check Approved 7/7/2021 KHUONG TRUONG
Issued 9/14/2021 APPLICANT
CofO in Progress 8/24/2023 SCOTT FINNILA
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/21/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 4/21/2021 RENZ SORIANO

Contact Information

Contractor Santa Fe Contractors Inc; Lic. No.: 951293-B 34385 ACTON CANYON RD      ACTON, CA 93510
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/31/2023 Partial Approval JEFFREY MEAD
Grounding or Bonding 5/31/2023 Approved JEFFREY MEAD
Footing/Foundation/Slab 6/13/2023 Corrections Issued SCOTT FINNILA
METHANE-Barrier 6/13/2023 Not Ready for Inspection SCOTT FINNILA
METHANE-Subgrade 6/13/2023 Not Ready for Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 7/6/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved LILIANA PORTILLO
METHANE-Rough 7/6/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/18/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 7/18/2023 Corrections Issued LILIANA PORTILLO
Green Building Rough 7/18/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/18/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 8/8/2023 Approved LILIANA PORTILLO
Final 8/8/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 8/8/2023 Approved LILIANA PORTILLO
Green Building Final 8/8/2023 Approved LILIANA PORTILLO
METHANE-Barrier 8/8/2023 Approved LILIANA PORTILLO
METHANE-Subgrade 8/8/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 8/8/2023 Not Required LILIANA PORTILLO
Smoke Detectors 8/8/2023 No Access for Inspection LILIANA PORTILLO
ELECTRICAL-Final 8/23/2023 Approved LILIANA PORTILLO
Final 8/23/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 8/23/2023 Approved LILIANA PORTILLO
PLUMBING-Final 8/23/2023 Approved LILIANA PORTILLO
Smoke Detectors 8/23/2023 Approved LILIANA PORTILLO