662 E INDIANA AVE 90291

Certificate Information: 662 E INDIANA AVE 90291

Application / Permit
21010-30000-01677
Plan Check / Job No.
B21WL01483
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New det. ADU (700 sf) over 2-car garage (450 sf) and 1-car carport (250 sf) per LAMC 12.22 A.33 (c)-(d) at rear of the lot.
Permit Issued
Issued on 11/28/2022
Issuing Office
Metro
Current Status
Issued on 11/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/12/2021 REZA HAGHIGHAT
Corrections Issued 5/25/2021 REZA HAGHIGHAT
Quality Review Completed 6/7/2021 TARIK SAOUD
Applicant returned to address corrections 5/25/2022 REZA HAGHIGHAT
Plan Check Approved 9/8/2022 REZA HAGHIGHAT
Building Plans Picked Up 9/9/2022 APPLICANT
Issued 11/28/2022 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/7/2021 GILBERT URREA
Coastal Zone Cleared 2/10/2022 DALIA MOKAYED
Specific Plan Cleared 2/10/2022 DALIA MOKAYED
ZA Case Cleared 2/10/2022 DALIA MOKAYED
ZA Case Cleared 2/10/2022 DALIA MOKAYED
Construction near power lines Cleared 2/16/2022 RIDWAN HARDY
Low Impact Development Cleared 3/22/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/21/2022 HISASHI KOBAYAKAWA
Address approval Cleared 6/22/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/22/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/22/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Jato Consultants Inc; Lic. No.: 1045767-B 21492 COUNTRYSIDE DR      LAKE FOREST, CA 92630
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/5/2024 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 4/19/2024 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 4/22/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 4/24/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Not Ready for Inspection HERBERT GIRON
Wood Frame 9/11/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 10/16/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 10/23/2024 Approved HERBERT GIRON
Deputy Drilled-In Anchors 10/28/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 10/30/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 10/31/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/13/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 11/13/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 11/15/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/22/2024 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 11/22/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/26/2024 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 11/26/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 12/2/2024 Approved BOBBY KEY
PLUMBING-Rough 12/2/2024 Approved BOBBY KEY
Insulation 12/18/2024 No Access for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 12/18/2024 No Access for Inspection HERBERT GIRON
BUILDING-Rough-Frame 12/20/2024 Corrections Issued HERBERT GIRON
Green Building Rough 12/20/2024 Corrections Issued HERBERT GIRON
Verify Sprinkler Sign Off 12/20/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/3/2025 Conditional Approval MICHAEL ALLEN
Green Building Rough 1/3/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/3/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 1/8/2025 Approved HERBERT GIRON
Final 1/8/2025 Corrections Issued HERBERT GIRON
Insulation 1/13/2025 Approved HERBERT GIRON
Drywall Nailing 1/23/2025 Approved MICHAEL ALLEN
Light Gage Steel Frame 1/23/2025 Approved MICHAEL ALLEN
Special/Order Compliance 1/23/2025 Corrections Issued MICHAEL ALLEN
Special/Order Compliance 2/26/2025 Approved HERBERT GIRON