664 E INDIANA AVE 90291

Certificate Information: 664 E INDIANA AVE 90291

Application / Permit
21010-30000-01676
Plan Check / Job No.
B21WL01483
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story S.F.D. (3,400 sf) with roof deck (700sf) and att. trellised roof patio cover (224 sf) at rear side
Permit Issued
Issued on 11/28/2022
Issuing Office
Metro
Current Status
Issued on 11/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 5/12/2021 REZA HAGHIGHAT
Corrections Issued 5/25/2021 REZA HAGHIGHAT
Quality Review Completed 6/7/2021 TARIK SAOUD
Applicant returned to address corrections 5/25/2022 REZA HAGHIGHAT
Plan Check Approved 9/8/2022 REZA HAGHIGHAT
Building Plans Picked Up 9/9/2022 APPLICANT
Issued 11/28/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/28/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/2/2021 DINAH GARIN
Hydrant and Access approval Cleared 12/7/2021 GILBERT URREA
Coastal Zone Cleared 2/10/2022 DALIA MOKAYED
Specific Plan Cleared 2/10/2022 DALIA MOKAYED
ZA Case Cleared 2/10/2022 DALIA MOKAYED
ZA Case Cleared 2/10/2022 DALIA MOKAYED
Low Impact Development Cleared 3/22/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/21/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Jato Consultants Inc; Lic. No.: 1045767-B 21492 COUNTRYSIDE DR      LAKE FOREST, CA 92630
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/25/2023 No Access for Inspection EVAN COOPER
Special/Order Compliance 4/26/2023 Approved EVAN COOPER
Special/Order Compliance 5/12/2023 Partial Inspection EVAN COOPER
Special/Order Compliance 5/15/2023 Corrections Issued EVAN COOPER
Pre-Inspection 12/5/2023 Partial Inspection HERBERT GIRON
Pre-Inspection 1/18/2024 Partial Inspection HERBERT GIRON
Sewer 4/1/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 4/3/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 4/19/2024 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 4/22/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 4/24/2024 Approved HERBERT GIRON
Deputy Reinf. Concrete 5/22/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Corrections Issued HERBERT GIRON
Wood Frame 9/11/2024 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 9/13/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 10/16/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 10/23/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 10/30/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 10/31/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/13/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 11/13/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 11/15/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/22/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 11/22/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/26/2024 Corrections Issued HERBERT GIRON
Underground Mechanical 11/26/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 12/2/2024 Approved BOBBY KEY
PLUMBING-Rough 12/2/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 12/20/2024 Corrections Issued HERBERT GIRON
Green Building Rough 12/20/2024 Corrections Issued HERBERT GIRON
Insulation 12/20/2024 Corrections Issued HERBERT GIRON
Verify Sprinkler Sign Off 12/20/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/3/2025 Conditional Approval MICHAEL ALLEN
Green Building Rough 1/3/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/3/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 1/8/2025 Approved HERBERT GIRON
Final 1/8/2025 Corrections Issued HERBERT GIRON
Insulation 1/13/2025 Approved HERBERT GIRON
Deputy Wood Construction 1/21/2025 Conditional Approval BOBBY KEY
Drywall Nailing 1/23/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 3/2/2026 Corrections Issued MICHAEL ALLEN
Special/Order Compliance 5/4/2026 Corrections Issued RUBEN RIVAS