11008 S MCKINLEY AVE 90059

Certificate Information: 11008 S MCKINLEY AVE 90059

Application / Permit
21010-30000-01594
Plan Check / Job No.
B21WL01408
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New one story ADU per WFPP
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 4/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 RICHARD GARCIA
Corrections Issued 5/1/2021 RICHARD GARCIA
Plan Check Approved 9/30/2021 RICHARD GARCIA
Issued 10/15/2021 APPLICANT
CofO in Progress 4/4/2023 JOHN KLARIN
Permit Finaled 4/13/2023 ANSON MAGLASANG
CofO Issued 4/13/2023 ANSON MAGLASANG
Permit Finaled 4/13/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/10/2021 MSTAFA AL-MSARI
Eng Process Fee Ord 176,300 Cleared 6/11/2021 MSTAFA AL-MSARI
Sewer availability Cleared 6/11/2021 MSTAFA AL-MSARI
Hydrant and Access approval Cleared 8/26/2021 GILBERT URREA
Low Impact Development Cleared 9/1/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/2/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/26/2021 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 4/12/2022 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 6/27/2022 Partial Approval JOHN KLARIN
PLUMBING-Rough 6/27/2022 Partial Approval JOHN KLARIN
Underground Mechanical 6/27/2022 Partial Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/1/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 7/1/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/2/2022 Not Ready for Inspection JOHN KLARIN
Green Building Rough 8/2/2022 Approved JOHN KLARIN
Verify Sprinkler Sign Off 8/2/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Partial Approval JOHN KLARIN
Underground Mechanical 8/26/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 9/16/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Approved JOHN KLARIN
PLUMBING-Rough 9/16/2022 Approved JOHN KLARIN
Gas Test 10/4/2022 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 10/4/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 10/4/2022 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/4/2022 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 10/12/2022 Approved ALIZAH MAYAGOITIA
Insulation 10/12/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 10/19/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 10/19/2022 Approved JOHN KLARIN
ELECTRICAL-Final 11/15/2022 Approved JOHN KLARIN
Gas Test 11/15/2022 Approved JOHN KLARIN
HVAC-Final 11/15/2022 Approved JOHN KLARIN
Service/Power Release 11/15/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 11/15/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/23/2022 Approved JOHN KLARIN
Final 11/23/2022 Corrections Issued JOHN KLARIN
Green Building Final 11/23/2022 Corrections Issued JOHN KLARIN
PLUMBING-Final 11/23/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 11/23/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 12/19/2022 Approved JOHN KLARIN
Final 3/1/2023 Not Ready for Inspection JOHN KLARIN
Service/Power Release 3/1/2023 Corrections Issued JOHN KLARIN
Final 3/23/2023 Corrections Issued JOHN KLARIN
Service/Power Release 3/23/2023 Not Ready for Inspection JOHN KLARIN
Final 4/3/2023 OK to Issue CofO JOHN KLARIN
Service/Power Release 4/3/2023 Approved JOHN KLARIN