1017 N KAGAWA ST 90272

Certificate Information: 1017 N KAGAWA ST 90272

Application / Permit
21010-30000-01536
Plan Check / Job No.
B21WL01364
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD (3,808 SF) (5-BEDROOM ; 5-FULL-BATHROOM ; ONE 1/2-BATH) W. ATT. 2-CAR GARAGE (380 SF) & ATT. COVERED PORCH AT FRONT AND REAR (103 SF)
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 REZA HAGHIGHAT
Corrections Issued 4/12/2021 REZA HAGHIGHAT
Quality Review Completed 4/23/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 5/11/2021 REZA HAGHIGHAT
Applicant returned to address corrections 10/7/2021 REZA HAGHIGHAT
Applicant returned to address corrections 11/3/2021 REZA HAGHIGHAT
Applicant returned to address corrections 3/15/2022 REZA HAGHIGHAT
Applicant returned to address corrections 3/21/2022 REZA HAGHIGHAT
Plan Check Approved 6/16/2022 REZA HAGHIGHAT
Issued 6/16/2022 APPLICANT
Building Plans Picked Up 7/26/2022 APPLICANT
CofO in Progress 8/28/2023 ARAM AVEDISIAN
Permit Finaled 9/6/2023 DANIEL ORRANTE
Permit Finaled 9/6/2023 DANIEL ORRANTE
CofO Issued 9/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2021 NIKTA MOUSAVI
Sewer availability Cleared 6/7/2021 NIKTA MOUSAVI
Hydrant and Access approval Cleared 8/19/2021 ROBERT DUFF
Low Impact Development Cleared 8/25/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/26/2021 NIKTA MOUSAVI
Permit Cleared 11/17/2021 NIKTA MOUSAVI
Trees in Parkway Cleared 2/23/2022 ADALBERTO VERA
GPI Written Notices Cleared 3/21/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 3/21/2022 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/15/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/17/2022 Corrections Issued KEVIN SARGSYAN
Sewer 8/17/2022 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/18/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/18/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/22/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/29/2022 Corrections Issued KEVIN SARGSYAN
Deputy Wood Construction 8/29/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/3/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/7/2022 Approved CLAYTON GRAHAM
HVAC-Rough 10/20/2022 Approved KEVIN SARGSYAN
Shower Pan 10/20/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/21/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 10/28/2022 Partial Approval KEVIN SARGSYAN
Green Building Rough 11/3/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/3/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 11/8/2022 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 11/8/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/9/2022 Approved KEVIN SARGSYAN
Insulation 1/23/2023 Approved BRENDAN LOONEY
Drywall Nailing 2/3/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Final 4/28/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 5/5/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 6/5/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 6/5/2023 Approved OGANES TARAKHCHYAN
Verify Rec and Parks Fee Memo 6/7/2023 Approved OGANES TARAKHCHYAN
Gas Test 6/8/2023 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/28/2023 Approved ARAM AVEDISIAN
Final 8/28/2023 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 8/28/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 8/28/2023 Approved ARAM AVEDISIAN
Smoke Detectors 8/28/2023 Approved ARAM AVEDISIAN