5309-5309 3/4 N BEN AVE 91607
Certificate Information: 5309-5309 3/4 N BEN AVE 91607
- Application / Permit
- 21010-30000-01514
- Plan Check / Job No.
- B21WL01358
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2 story duplex with ADU (Rear Building)
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 4/12/2021 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 4/12/2021 | CHIHARU SUZUKI |
| Plan Check Approved | 8/16/2022 | HOOMAN HAJIZADEH |
| Issued | 8/22/2022 | APPLICANT |
| Building Plans Picked Up | 8/23/2022 | APPLICANT |
| CofO in Progress | 2/20/2024 | KIRK SANDERS |
| CofO Issued | 2/29/2024 | RUBEN SALAS |
| Permit Finaled | 2/29/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | GABRIEL ROBLES |
| Highway dedication | Cleared | 4/14/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 6/5/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 7/30/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/31/2021 | ABDULLAH SADOZAI |
| Specific Plan | Cleared | 8/9/2022 | ASHLEY RODARTE |
| Building over 36-ft | Cleared | 8/10/2022 | CALOSHA APPROVED |
| Sewer availability | Cleared | 8/10/2022 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Onward Builders Llc; Lic. No.: 1084275-B | 750 N SAN VICENTE BLVD STE 800 WEST HOLLYWOOD, CA 90069 |
| Engineer | Kumar,, Krishna C V; Lic. No.: M22176 | 3877 DWIGGINS ST LOS ANGELES, CA 90063 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 10/6/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 10/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 10/17/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/18/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/28/2022 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 11/14/2022 | Conditional Approval | DAVID MATSON |
| Deputy Steel/Welding | 11/21/2022 | Conditional Approval | MICHAEL SMITH |
| Wood Frame | 12/6/2022 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 1/13/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 4/18/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 4/19/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 4/19/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/11/2023 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 5/11/2023 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 5/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/17/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 5/17/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/17/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 5/17/2023 | Approved | JACK KARGODORIAN |
| Insulation | 5/30/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/30/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 6/13/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 6/21/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 6/21/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/27/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 6/27/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 12/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 12/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 12/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 12/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 2/6/2024 | Approved | KIRK SANDERS |
| Final | 2/6/2024 | Not Ready for Inspection | KIRK SANDERS |
| Gas Test | 2/6/2024 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 2/6/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 2/6/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 2/6/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 2/6/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/14/2024 | Corrections Issued | KIRK SANDERS |
| Gas Test | 2/14/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 2/14/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 2/14/2024 | Approved | KIRK SANDERS |
| Final | 2/16/2024 | OK to Issue CofO | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 2/16/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 2/16/2024 | Approved | KIRK SANDERS |