3021 S EARLMAR DR 90064
Certificate Information: 3021 S EARLMAR DR 90064
- Application / Permit
- 21010-30000-01315
- Plan Check / Job No.
- B21WL01201
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story S.F.R. w/ basement and attached garage
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofO Issued on 10/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | TARIK SAOUD |
| Corrections Issued | 3/31/2021 | TARIK SAOUD |
| Quality Review Completed | 4/9/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/4/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 8/6/2021 | REZA HAGHIGHAT |
| Issued | 8/31/2021 | APPLICANT |
| CofO in Progress | 10/17/2023 | CLAYTON GRAHAM |
| Permit Finaled | 10/28/2023 | DANIEL ORRANTE |
| CofO Issued | 10/28/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/19/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 5/20/2021 | JOHN CONNEALLY |
| Frnt yard landscape/Water mgmt | Cleared | 6/4/2021 | DENZEL HENDERSON |
| Specific Plan | Cleared | 6/14/2021 | VALERIA CEJA |
| Low Impact Development | Cleared | 6/18/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/23/2021 | DENNIS BRAGIN |
| Excavation more than 5-ft deep | Cleared | 8/4/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 8/4/2021 | TARIK SAOUD |
Contact Information
| Architect | , ; Lic. No.: C34496 | 9856 VIDOR DRIVE LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2021 | Partial Inspection | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 9/16/2021 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/26/2021 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/29/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/23/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Gunite | 11/23/2021 | Approved | OGANES TARAKHCHYAN |
| Reinforced Concrete Frame | 11/23/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Reinforced Masonry Frame | 11/23/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/27/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/24/2022 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 2/24/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 2/24/2022 | Approved | EVAN COOPER |
| Deputy Wood Construction | 3/4/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 3/18/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/22/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 6/15/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/22/2022 | Partial Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/3/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/5/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/5/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/10/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 8/18/2022 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 8/19/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/24/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 8/24/2022 | Approved | JOHN KIDWELL |
| METHANE-Rough | 8/24/2022 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 8/24/2022 | Approved | JOHN KIDWELL |
| Insulation | 9/9/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/21/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/6/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 12/6/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 1/27/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Sewer | 2/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| Underground Mechanical | 2/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| Sewer | 2/7/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/1/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 5/1/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 5/1/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/2/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 5/2/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 5/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/4/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 5/4/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 5/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 6/13/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 7/28/2023 | Conditional Approval | CLAYTON GRAHAM |
| Gas Test | 7/28/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 7/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 7/28/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Service/Power Release | 7/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 7/28/2023 | Approved | CLAYTON GRAHAM |
| Final | 10/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 10/10/2023 | Approved | CLAYTON GRAHAM |
| Green Building Final | 10/10/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 10/10/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 10/16/2023 | Approved | CLAYTON GRAHAM |
| Final | 10/16/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| Service/Power Release | 10/16/2023 | Approved | CLAYTON GRAHAM |