481 N BUNDY DR 90049

Certificate Information: 481 N BUNDY DR 90049

Application / Permit
21010-30000-01313
Plan Check / Job No.
B21WL01197
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
new pool gym (rec room)
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 TARIK SAOUD
Corrections Issued 4/7/2021 TARIK SAOUD
Quality Review Completed 4/14/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/15/2021 TARIK SAOUD
Applicant returned to address corrections 7/6/2021 TARIK SAOUD
Applicant returned to address corrections 10/14/2021 TARIK SAOUD
Plan Check Approved 11/22/2021 TARIK SAOUD
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 2/24/2022 APPLICANT
CofO in Progress 7/8/2022 CARLOS MATAMOROS
Permit Finaled 7/18/2022 DANIEL ORRANTE
CofO Issued 7/18/2022 DANIEL ORRANTE
Permit Finaled 7/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/30/2021 TRACY TATE
Hydrant and Access approval Cleared 9/2/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/4/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 10/6/2021 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 10/14/2021 TARIK SAOUD
Construction near power lines Cleared 10/29/2021 RIDWAN HARDY

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Ardsley Construction Co; Lic. No.: 248586-B 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/29/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 12/15/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 12/22/2021 Partial Approval BRENDAN LOONEY
Special/Order Compliance 1/11/2022 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 3/24/2022 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 3/24/2022 Approved CARLOS MATAMOROS
Green Building Rough 3/24/2022 Approved CARLOS MATAMOROS
Drywall Nailing 4/4/2022 Approved CHRISTOPHER WILSON
Insulation 4/4/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 5/25/2022 Corrections Issued CARLOS MATAMOROS
HVAC-Final 5/25/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Final 5/25/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/8/2022 Approved CARLOS MATAMOROS
Final 7/8/2022 OK to Issue CofO CARLOS MATAMOROS
Footing/Foundation/Slab 7/8/2022 Approved CARLOS MATAMOROS
Green Building Final 7/8/2022 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved CARLOS MATAMOROS
Service/Power Release 7/8/2022 Approved CARLOS MATAMOROS
Smoke Detectors 7/8/2022 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/8/2022 Approved CARLOS MATAMOROS