518 N MANSFIELD AVE 90036
Certificate Information: 518 N MANSFIELD AVE 90036
- Application / Permit
- 21010-30000-01286
- Plan Check / Job No.
- B21WL01157
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ADU per LAMC 12.22A33(c) & (d) in the rear of the lot.
- Permit Issued
- Issued on 8/30/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 4/6/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 6/7/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/26/2022 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 8/29/2022 | JAHANSHAH POURHASSAN |
| Issued | 8/30/2022 | APPLICANT |
| Building Plans Picked Up | 9/7/2022 | APPLICANT |
| CofO in Progress | 8/5/2024 | BRIAN SULLIVAN |
| Permit Finaled | 1/16/2025 | DEROLD HAUFF |
| CofO Issued | 1/16/2025 | DEROLD HAUFF |
| Permit Finaled | 1/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | CINDY QI |
| Sewer availability | Cleared | 3/1/2022 | CINDY QI |
| Low Impact Development | Cleared | 5/11/2022 | JULIAN SUNG |
| Hydrant and Access approval | Cleared | 5/12/2022 | LAURINDA MEADE |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yates,, Gerald Lee; Lic. No.: C73972 | 6309 DEL AMO BLVD LAKEWOOD, CA 90713 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 11/15/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/15/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/30/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 11/30/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/14/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/14/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 2/14/2023 | Approved | STUART CHAPMAN |
| METHANE-Rough | 2/14/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/14/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/14/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/21/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/21/2023 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 3/24/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 3/24/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/31/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 3/31/2023 | Approved | RAUL BARAJAS |
| Underground Mechanical | 6/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/20/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/29/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Final | 1/31/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 1/31/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 1/31/2024 | Approved | BRIAN SULLIVAN |
| Final | 8/2/2024 | OK to Issue CofO | BRIAN SULLIVAN |