320 N CLIFFWOOD AVE 90049

Certificate Information: 320 N CLIFFWOOD AVE 90049

Application / Permit
21010-30000-01271
Plan Check / Job No.
B21WL01149
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD (7,449 sf) w./ one level basement (1,858 sf) and att. 3-car garage (777 sf)
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 REZA HAGHIGHAT
Corrections Issued 3/22/2021 REZA HAGHIGHAT
Quality Review Completed 4/1/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 8/6/2021 REZA HAGHIGHAT
Issued 8/18/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT
CofO in Progress 3/11/2024 KEVIN SARGSYAN
Permit Finaled 3/18/2024 DANIEL ORRANTE
CofO Issued 3/18/2024 DANIEL ORRANTE
Permit Finaled 3/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 4/13/2021 DINAH GARIN
Sewer availability Cleared 4/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/15/2021 DINAH GARIN
Trees in Parkway Cleared 4/26/2021 JOHN KIM
Hydrant and Access approval Cleared 5/7/2021 JOHN CONNEALLY
Construction near power lines Cleared 7/9/2021 RIDWAN HARDY
Disturb/Remove Protected Trees Cleared 7/15/2021 REZA HAGHIGHAT
Low Impact Development Cleared 7/28/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/28/2021 DINAH GARIN
Excavation more than 5-ft deep Cleared 8/6/2021 CALOSHA APPROVED
GPI Written Notices Cleared 8/6/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 8/6/2021 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361
Geologist , ; Lic. No.: GEO861    7438 SHIRLEY AVE    RESEDA, CA 91335

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/25/2022 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 3/15/2022 Partial Approval ANDREW NAVE
Special/Order Compliance 3/15/2022 Partial Inspection PATRICK QUALEY
Footing/Foundation/Slab 4/1/2022 Conditional Approval JOHN KIDWELL
Underground Mechanical 5/17/2022 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 5/25/2022 Approved JUAN VALENZUELA
Footing/Foundation/Slab 5/25/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 6/14/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 8/3/2022 Corrections Issued PATRICK QUALEY
HVAC-Rough 8/5/2022 Approved JUAN VALENZUELA
ELECTRICAL-Rough 8/9/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 8/22/2022 Not Ready for Inspection JUAN VALENZUELA
Shower Pan 8/22/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/23/2022 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Approved JUAN VALENZUELA
Green Building Rough 8/23/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 8/23/2022 Conditional Approval JUAN VALENZUELA
Verify Sprinkler Sign Off 8/23/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/25/2022 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 8/26/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 8/29/2022 Conditional Approval JUAN VALENZUELA
Green Building Rough 8/29/2022 Approved JUAN VALENZUELA
Insulation 8/29/2022 Approved JUAN VALENZUELA
Drywall Nailing 9/1/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 9/1/2022 Not Ready for Inspection JUAN VALENZUELA
Drywall Nailing 9/2/2022 Conditional Approval JUAN VALENZUELA
Underground Mechanical 10/11/2022 Partial Approval JUAN VALENZUELA
Gas Test 11/23/2022 Approved MICHAEL PELHAM
Sewer 11/23/2022 Approved MICHAEL PELHAM
Special/Order Compliance 11/23/2022 Partial Inspection JEREMY TODD
Gas Test 6/6/2023 Approved KEVIN SARGSYAN
PLUMBING-Final 9/1/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 9/6/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/29/2024 Approved EVAN COOPER
HVAC-Final 1/29/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 2/26/2024 Approved ARAM AVEDISIAN
Drywall Nailing 2/26/2024 Approved ARAM AVEDISIAN
Final 2/26/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 2/26/2024 Approved ARAM AVEDISIAN
Green Building Rough 2/26/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 2/26/2024 Approved ARAM AVEDISIAN
Final 2/27/2024 Corrections Issued KEVIN SARGSYAN
Service/Power Release 2/27/2024 Not Ready for Inspection KEVIN SARGSYAN
Pre-Inspection 2/28/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 2/29/2024 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 2/29/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 3/1/2024 Conditional Approval KEVIN SARGSYAN
Service/Power Release 3/1/2024 Approved KEVIN SARGSYAN
Final 3/5/2024 Not Ready for Inspection KEVIN SARGSYAN
Final 3/11/2024 OK to Issue CofO KEVIN SARGSYAN