320 N CLIFFWOOD AVE 90049
Certificate Information: 320 N CLIFFWOOD AVE 90049
- Application / Permit
- 21010-30000-01271
- Plan Check / Job No.
- B21WL01149
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-story SFD (7,449 sf) w./ one level basement (1,858 sf) and att. 3-car garage (777 sf)
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | REZA HAGHIGHAT |
| Corrections Issued | 3/22/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 4/1/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/6/2021 | REZA HAGHIGHAT |
| Issued | 8/18/2021 | APPLICANT |
| Building Plans Picked Up | 12/9/2021 | APPLICANT |
| CofO in Progress | 3/11/2024 | KEVIN SARGSYAN |
| Permit Finaled | 3/18/2024 | DANIEL ORRANTE |
| CofO Issued | 3/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 4/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/13/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 4/26/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/7/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 7/9/2021 | RIDWAN HARDY |
| Disturb/Remove Protected Trees | Cleared | 7/15/2021 | REZA HAGHIGHAT |
| Low Impact Development | Cleared | 7/28/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | DINAH GARIN |
| Excavation more than 5-ft deep | Cleared | 8/6/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/6/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 8/6/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | , ; Lic. No.: GEO861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/25/2022 | Partial Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/15/2022 | Partial Approval | ANDREW NAVE |
| Special/Order Compliance | 3/15/2022 | Partial Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/1/2022 | Conditional Approval | JOHN KIDWELL |
| Underground Mechanical | 5/17/2022 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/25/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 6/14/2022 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 8/3/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Rough | 8/5/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 8/9/2022 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 8/22/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Shower Pan | 8/22/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/23/2022 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 8/23/2022 | Conditional Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 8/23/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/25/2022 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/26/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 8/29/2022 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 8/29/2022 | Approved | JUAN VALENZUELA |
| Insulation | 8/29/2022 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 9/1/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 9/2/2022 | Conditional Approval | JUAN VALENZUELA |
| Underground Mechanical | 10/11/2022 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 11/23/2022 | Approved | MICHAEL PELHAM |
| Sewer | 11/23/2022 | Approved | MICHAEL PELHAM |
| Special/Order Compliance | 11/23/2022 | Partial Inspection | JEREMY TODD |
| Gas Test | 6/6/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 9/1/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/6/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/29/2024 | Approved | EVAN COOPER |
| HVAC-Final | 1/29/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 2/26/2024 | Approved | ARAM AVEDISIAN |
| Final | 2/26/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 2/26/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 2/26/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/26/2024 | Approved | ARAM AVEDISIAN |
| Final | 2/27/2024 | Corrections Issued | KEVIN SARGSYAN |
| Service/Power Release | 2/27/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 2/28/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 2/29/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Service/Power Release | 2/29/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 3/1/2024 | Conditional Approval | KEVIN SARGSYAN |
| Service/Power Release | 3/1/2024 | Approved | KEVIN SARGSYAN |
| Final | 3/5/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 3/11/2024 | OK to Issue CofO | KEVIN SARGSYAN |