3733 S MOORE ST 90066

Certificate Information: 3733 S MOORE ST 90066

Application / Permit
21010-30000-01261
Plan Check / Job No.
B21WL01141
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-story Det. ADU (327 sf) at rear of the lot to replace (e) garage per eng. design & per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 REZA HAGHIGHAT
Corrections Issued 3/22/2021 REZA HAGHIGHAT
Quality Review Completed 4/1/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/25/2021 REZA HAGHIGHAT
Plan Check Approved 7/1/2021 REZA HAGHIGHAT
Building Plans Picked Up 7/2/2021 APPLICANT
Issued 7/21/2021 APPLICANT
CofO in Progress 4/21/2022 PATRICK QUALEY
CofO Issued 4/25/2022 DANIEL ORRANTE
Permit Finaled 4/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 4/28/2021 YVAINNE GALSIM
Address approval Cleared 5/4/2021 DENNIS BRAGIN
Sewer availability Cleared 5/4/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 5/5/2021 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 5/5/2021 DENNIS BRAGIN
Specific Plan Cleared 5/12/2021 FREDDY GARCIA
Hydrant and Access approval Cleared 5/22/2021 MATTHEW CRAIG
Construction near power lines Cleared 5/29/2021 WALTER RAMIREZ
GPI Written Notices Cleared 6/25/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 6/25/2021 REZA HAGHIGHAT

Contact Information

Architect Keck,, Krystyan Elizabeth; Lic. No.: C29385 12322 GREENE AVENUE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/17/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/20/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 8/24/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/25/2021 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/31/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/2/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/2/2021 Approved ENRIQUE MIRELES
Green Building Rough 11/2/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/2/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 11/2/2021 Approved ENRIQUE MIRELES
Insulation 11/24/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/24/2021 Approved ENRIQUE MIRELES
Drywall Nailing 12/8/2021 Approved JOHN KAYON
Underground Mechanical 1/7/2022 Approved RYAN SALAZAR
Final 3/15/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 3/15/2022 Approved DAVID FEILER
Green Building Final 3/15/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Not Ready DAVID FEILER
Service/Power Release 3/15/2022 Corrections Issued DAVID FEILER
Smoke Detectors 3/15/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 4/7/2022 Approved PATRICK QUALEY
Final 4/7/2022 Corrections Issued PATRICK QUALEY
Green Building Final 4/7/2022 Approved PATRICK QUALEY
HVAC-Final 4/7/2022 Approved PATRICK QUALEY
PLUMBING-Final 4/7/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved PATRICK QUALEY
Service/Power Release 4/7/2022 Corrections Issued PATRICK QUALEY
Smoke Detectors 4/7/2022 Approved PATRICK QUALEY
Final 4/21/2022 OK to Issue CofO PATRICK QUALEY
Service/Power Release 4/21/2022 Approved PATRICK QUALEY