8521 W AIRDROME ST 90035
Certificate Information: 8521 W AIRDROME ST 90035
- Application / Permit
- 21010-30000-01256
- Plan Check / Job No.
- B21WL01137
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | TARIK SAOUD |
| Corrections Issued | 4/13/2021 | TARIK SAOUD |
| Quality Review Completed | 4/23/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/1/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 8/6/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | EVAN COOPER |
| Permit Finaled | 10/4/2022 | DANIEL ORRANTE |
| CofO Issued | 10/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 5/20/2021 | JOHN KIM |
| Address approval | Cleared | 5/21/2021 | WALLIE JONG |
| Permit | Cleared | 5/21/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 6/15/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/29/2021 | ANDRES COVARRUBIAS |
| Frnt yard landscape/Water mgmt | Cleared | 7/1/2021 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 7/7/2021 | STEVE MELGAR |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/8/2021 | Partial Approval | EVAN COOPER |
| METHANE-Subgrade | 9/10/2021 | Approved | EVAN COOPER |
| METHANE-Barrier | 9/20/2021 | Approved | EVAN COOPER |
| Sewer | 9/20/2021 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 9/29/2021 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2021 | Not Ready for Inspection | EVAN COOPER |
| Deputy Wood Construction | 11/12/2021 | Conditional Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 12/7/2021 | Approved | EVAN COOPER |
| METHANE-Rough | 12/8/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 12/8/2021 | Approved | EVAN COOPER |
| Shower Pan | 12/8/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 12/13/2021 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 12/17/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 1/11/2022 | Approved | EVAN COOPER |
| Green Building Rough | 1/11/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/11/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 1/11/2022 | Approved | EVAN COOPER |
| Insulation | 2/9/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 2/17/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/17/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/25/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/25/2022 | Approved | EVAN COOPER |
| Green Building Final | 5/6/2022 | Approved | EVAN COOPER |
| HVAC-Final | 5/6/2022 | Approved | EVAN COOPER |
| Service/Power Release | 5/6/2022 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 5/24/2022 | Not Ready for Inspection | EVAN COOPER |
| Final | 7/8/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 7/8/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 7/8/2022 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 7/8/2022 | Approved | EVAN COOPER |
| Final | 7/18/2022 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | EVAN COOPER |
| Final | 9/19/2022 | Not Ready for Inspection | ANDREW NAVE |
| Service/Power Release | 9/19/2022 | Not Ready for Inspection | ANDREW NAVE |
| Service/Power Release | 9/22/2022 | Approved | EVAN COOPER |
| Service/Power Release | 9/27/2022 | Approved | MICHAEL PELHAM |
| Final | 9/28/2022 | OK to Issue CofO | EVAN COOPER |