1826 S COCHRAN AVE 90019

Certificate Information: 1826 S COCHRAN AVE 90019

Application / Permit
21010-30000-01108
Plan Check / Job No.
B21WL01040
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) detached 1-story ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 2/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 FELIPE HERNANDEZ
Corrections Issued 3/16/2021 FELIPE HERNANDEZ
Quality Review Completed 3/25/2021 TARIK SAOUD
Applicant returned to address corrections 5/21/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 8/24/2021 FELIPE HERNANDEZ
Plan Check Approved 9/10/2021 FELIPE HERNANDEZ
Issued 9/28/2021 APPLICANT
CofO in Progress 2/23/2023 JOSE AVILA
CofO Issued 2/27/2023 DEROLD HAUFF
Permit Finaled 2/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Flood clearance Cleared 5/6/2021 BRYAN GATHUKA
Address approval Cleared 5/24/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/24/2021 JEANIE LAM
Sewer availability Cleared 5/24/2021 JEANIE LAM
Hydrant and Access approval Cleared 7/19/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 8/18/2021 JEANIE LAM
Low Impact Development Cleared 9/1/2021 JORGE MEJIA LEMUS

Contact Information

Architect Nguyen,, Timothy; Lic. No.: C35111 20 SALTAIRE      LAGUNA NIGUEL, CA 92677
Contractor Bravo Group Construction Co; Lic. No.: 1067972-B 732 S SPRING ST APT 1816      LOS ANGELES, CA 90014
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 11/12/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/12/2021 Corrections Issued JOSE AVILA
FLOOD-Elevation Certificate 11/19/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/19/2021 Corrections Issued JOSE AVILA
FLOOD-Elevation Certificate 12/1/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/1/2021 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Approved JOSE AVILA
PLUMBING-Rough 12/13/2021 Approved JOSE AVILA
Drywall Nailing 12/16/2021 Order to Comply Issued JOSE AVILA
Green Building Rough 12/16/2021 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Approved JOSE AVILA
ELECTRICAL-Rough 4/29/2022 Corrections Issued JOSE AVILA
HVAC-Final 4/29/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/29/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Corrections Issued JOSE AVILA
HVAC-Rough 5/4/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 5/4/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 5/6/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/6/2022 Approved JOSE AVILA
FLOOD-Proofing Certificate 5/6/2022 Not Ready for Inspection JOSE AVILA
HVAC-Rough 5/6/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/6/2022 Approved JOSE AVILA
Verify Sprinkler Sign Off 5/6/2022 Not Ready for Inspection JOSE AVILA
Deputy Wood Construction 5/10/2022 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 5/13/2022 Corrections Issued JOSE AVILA
FLOOD-Proofing Certificate 5/13/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 5/13/2022 Corrections Issued JOSE AVILA
Insulation 5/17/2022 No Access for Inspection JOSE AVILA
Insulation 5/31/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/31/2022 Approved JOSE AVILA
Drywall Nailing 6/6/2022 Approved JOSE AVILA
Drywall Nailing 8/31/2022 Approved JOSE AVILA
Interior/Exterior Lathing 8/31/2022 Approved JOSE AVILA
Shower Pan 8/31/2022 Approved JOSE AVILA
FLOOD-Elevation Certificate 9/6/2022 Approved JOSE AVILA
Footing/Foundation/Slab 9/6/2022 Approved JOSE AVILA
Deck 9/9/2022 Partial Approval JOSE AVILA
PLUMBING-Final 10/27/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 11/8/2022 Partial Inspection JOSE AVILA
ELECTRICAL-Final 11/8/2022 Corrections Issued JOSE AVILA
FLOOD-Proofing Certificate 11/8/2022 Approved JOSE AVILA
Final 11/8/2022 Corrections Issued JOSE AVILA
Green Building Final 11/8/2022 Corrections Issued JOSE AVILA
HVAC-Final 11/8/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 11/8/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved JOSE AVILA
Service/Power Release 11/8/2022 Approved JOSE AVILA
Smoke Detectors 11/8/2022 Approved JOSE AVILA
Verify Sprinkler Sign Off 11/8/2022 Partial Inspection JOSE AVILA
ELECTRICAL-Final 11/16/2022 Approved JOSE AVILA
HVAC-Final 11/16/2022 Approved JOSE AVILA
PLUMBING-Final 11/16/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 2/10/2023 Approved JOSE AVILA
Final 2/10/2023 Corrections Issued JOSE AVILA
Green Building Final 2/10/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 2/10/2023 Approved JOSE AVILA
Final 2/23/2023 OK to Issue CofO JOSE AVILA