1828 S COCHRAN AVE 90019
Certificate Information: 1828 S COCHRAN AVE 90019
- Application / Permit
- 21010-30000-01106
- Plan Check / Job No.
- B21WL01040
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to (E)xisting 1-story SFD
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 2/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 3/16/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 3/25/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/21/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/24/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 9/10/2021 | FELIPE HERNANDEZ |
| Issued | 9/28/2021 | APPLICANT |
| CofO in Progress | 2/23/2023 | JOSE AVILA |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
| CofO Issued | 2/26/2023 | DEROLD HAUFF |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/15/2021 | JEANIE LAM |
| ZI | Cleared | 4/15/2021 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 5/14/2021 | JOHN CONNEALLY |
| Flood clearance | Cleared | 6/28/2021 | BRYAN GATHUKA |
| Low Impact Development | Cleared | 8/12/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/18/2021 | JEANIE LAM |
Contact Information
| Architect | Nguyen,, Timothy; Lic. No.: C35111 | 20 SALTAIRE LAGUNA NIGUEL, CA 92677 |
| Contractor | Bravo Group Construction Co; Lic. No.: 1067972-B | 732 S SPRING ST APT 1816 LOS ANGELES, CA 90014 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 11/1/2021 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 11/1/2021 | Not Ready for Inspection | JOSE AVILA |
| FLOOD-Elevation Certificate | 11/5/2021 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 11/5/2021 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/12/2021 | Corrections Issued | JOSE AVILA |
| FLOOD-Elevation Certificate | 11/19/2021 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/19/2021 | Corrections Issued | JOSE AVILA |
| FLOOD-Elevation Certificate | 12/1/2021 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/1/2021 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 12/9/2021 | Partial Approval | JOSE AVILA |
| Special/Order Compliance | 12/9/2021 | Partial Inspection | JOSE AVILA |
| Wood Frame | 12/13/2021 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 4/29/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 5/4/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 5/4/2022 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 5/6/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 5/6/2022 | Approved | JOSE AVILA |
| FLOOD-Proofing Certificate | 5/6/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 5/6/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 5/6/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/6/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | JOSE AVILA |
| FLOOD-Proofing Certificate | 5/13/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Approved | JOSE AVILA |
| Green Building Rough | 5/13/2022 | Approved | JOSE AVILA |
| Insulation | 5/17/2022 | No Access for Inspection | JOSE AVILA |
| Insulation | 6/6/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 6/6/2022 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 8/31/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/31/2022 | Partial Approval | JOSE AVILA |
| Shower Pan | 8/31/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 10/27/2022 | Corrections Issued | JOSE AVILA |
| Gas Test | 11/7/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 11/7/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| FLOOD-Elevation Certificate | 11/8/2022 | Approved | JOSE AVILA |
| Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/8/2022 | Approved | JOSE AVILA |
| Green Building Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/8/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/16/2022 | Approved | JOSE AVILA |
| HVAC-Final | 11/16/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 11/16/2022 | Approved | JOSE AVILA |
| Service/Power Release | 12/5/2022 | Approved | JOSE AVILA |
| Final | 2/10/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 2/10/2023 | Approved | JOSE AVILA |
| Final | 2/23/2023 | OK to Issue CofO | JOSE AVILA |