2709 N ROSCOMARE ROAD 90077

Certificate Information: 2709 N ROSCOMARE ROAD 90077

Application / Permit
21010-30000-01083
Plan Check / Job No.
B21WL00992
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-Story ADU per CA Govt. Code 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), and (g)
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Issued on 9/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 DAVID CASTILLO
Corrections Issued 4/12/2021 DAVID CASTILLO
Quality Review Completed 4/26/2021 TARIK SAOUD
Applicant returned to address corrections 11/24/2021 DAVID CASTILLO
Plan Check Approved 3/9/2022 DAVID CASTILLO
Issued 3/9/2022 APPLICANT
Building Plans Picked Up 3/14/2022 APPLICANT
CofO in Progress 8/30/2024 CARLOS MATAMOROS
Permit Finaled 9/4/2024 RICHARD STEINBACH
CofO Issued 9/4/2024 RICHARD STEINBACH
Permit Finaled 9/4/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/8/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/8/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/8/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/8/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/8/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 5/8/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 5/10/2021 DENNIS BRAGIN
Sewer availability Cleared 5/10/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 6/29/2021 KURT CORRAL
Specific Plan Cleared 8/19/2021 OLGA AYALA
Low Impact Development Cleared 10/21/2021 TA ANH
Grading Pre-Inspection Cleared 11/24/2021 DAVID CASTILLO
Roof/Waste drainage to street Cleared 12/2/2021 DENNIS BRAGIN

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Hacienda Lopez Construction Inc; Lic. No.: 910123-B 2140 NADULA DRIVE      HACIENDA HEIGHTS, CA 91745
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2022 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 5/23/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 5/26/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/30/2022 Conditional Approval CARLOS MATAMOROS
ELECTRICAL-Rough 8/8/2022 Corrections Issued CHRISTOPHER WILSON
Gas Test 8/8/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/8/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 8/8/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/15/2022 Conditional Approval CHRISTOPHER WILSON
Structural Steel Frame 8/15/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Approved CARLOS MATAMOROS
Insulation 8/23/2022 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 10/14/2022 Corrections Issued CARLOS MATAMOROS
Gas Test 10/14/2022 Approved CARLOS MATAMOROS
Green Building Rough 10/14/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 10/14/2022 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/14/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 11/18/2022 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Approved CARLOS MATAMOROS
Green Building Rough 11/18/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/29/2023 Approved CARLOS MATAMOROS
HVAC-Rough 8/29/2023 Approved CARLOS MATAMOROS
Insulation 8/29/2023 Approved CARLOS MATAMOROS
Drywall Nailing 9/8/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 9/8/2023 Approved CARLOS MATAMOROS
Shower Pan 9/28/2023 Approved CHRISTOPHER WILSON
Deputy Wood Construction 4/22/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 5/28/2024 Not Ready for Inspection CARLOS MATAMOROS
Final 5/28/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 5/28/2024 Approved CARLOS MATAMOROS
Green Building Final 5/28/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 5/28/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 5/28/2024 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 5/28/2024 Approved CARLOS MATAMOROS
Smoke Detectors 5/28/2024 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 8/22/2024 Corrections Issued CARLOS MATAMOROS
Final 8/22/2024 Corrections Issued CARLOS MATAMOROS
Green Building Final 8/22/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 8/22/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 8/22/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 8/22/2024 Approved CARLOS MATAMOROS
Final 8/30/2024 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 8/30/2024 Approved CARLOS MATAMOROS