2709 N ROSCOMARE ROAD 90077
Certificate Information: 2709 N ROSCOMARE ROAD 90077
- Application / Permit
- 21010-30000-01083
- Plan Check / Job No.
- B21WL00992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-Story ADU per CA Govt. Code 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), and (g)
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 9/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | DAVID CASTILLO |
| Corrections Issued | 4/12/2021 | DAVID CASTILLO |
| Quality Review Completed | 4/26/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 11/24/2021 | DAVID CASTILLO |
| Plan Check Approved | 3/9/2022 | DAVID CASTILLO |
| Issued | 3/9/2022 | APPLICANT |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| CofO in Progress | 8/30/2024 | CARLOS MATAMOROS |
| Permit Finaled | 9/4/2024 | RICHARD STEINBACH |
| CofO Issued | 9/4/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/4/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/8/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/8/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/8/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/8/2021 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 5/8/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 5/10/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 6/29/2021 | KURT CORRAL |
| Specific Plan | Cleared | 8/19/2021 | OLGA AYALA |
| Low Impact Development | Cleared | 10/21/2021 | TA ANH |
| Grading Pre-Inspection | Cleared | 11/24/2021 | DAVID CASTILLO |
| Roof/Waste drainage to street | Cleared | 12/2/2021 | DENNIS BRAGIN |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Hacienda Lopez Construction Inc; Lic. No.: 910123-B | 2140 NADULA DRIVE HACIENDA HEIGHTS, CA 91745 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/29/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/23/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/26/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/28/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/30/2022 | Conditional Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/8/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Test | 8/8/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/8/2022 | Partial Approval | CHRISTOPHER WILSON |
| Wood Frame | 8/8/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 8/15/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Structural Steel Frame | 8/15/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 8/23/2022 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/14/2022 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 10/14/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 10/14/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/14/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 10/14/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/18/2022 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/18/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/29/2023 | Approved | CARLOS MATAMOROS |
| Insulation | 8/29/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 9/8/2023 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 9/8/2023 | Approved | CARLOS MATAMOROS |
| Shower Pan | 9/28/2023 | Approved | CHRISTOPHER WILSON |
| Deputy Wood Construction | 4/22/2024 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Final | 5/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 5/28/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/28/2024 | Approved | CARLOS MATAMOROS |
| Green Building Final | 5/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 5/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 5/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| Service/Power Release | 5/28/2024 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 5/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/22/2024 | Corrections Issued | CARLOS MATAMOROS |
| Final | 8/22/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 8/22/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 8/22/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 8/22/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 8/22/2024 | Approved | CARLOS MATAMOROS |
| Final | 8/30/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 8/30/2024 | Approved | CARLOS MATAMOROS |