331 S ANITA AVE 90049

Certificate Information: 331 S ANITA AVE 90049

Application / Permit
21010-30000-01082
Plan Check / Job No.
B21WL00989
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD (3,168 sf) w./ att. 2-car garage (373 sf), 1 level basement (2,280 sf), and rooftop deck
Permit Issued
Issued on 7/12/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 REZA HAGHIGHAT
Corrections Issued 5/10/2021 REZA HAGHIGHAT
Quality Review Completed 5/26/2021 TARIK SAOUD
Applicant returned to address corrections 10/21/2021 REZA HAGHIGHAT
Building Plans Picked Up 12/27/2021 APPLICANT
Plan Check Approved 4/6/2022 REZA HAGHIGHAT
Plan Check Approved 7/12/2023 REZA HAGHIGHAT
Issued 7/12/2023 APPLICANT
CofO in Progress 7/18/2025 HERBERT GIRON
Permit Finaled 7/29/2025 RICHARD STEINBACH
CofO Issued 7/29/2025 RICHARD STEINBACH
Permit Finaled 7/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 6/4/2021 DINAH GARIN
ZA Case Cleared 6/7/2021 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 6/14/2021 DINAH GARIN
Sewer availability Cleared 6/14/2021 DINAH GARIN
Trees in Parkway Cleared 7/1/2021 JOHN KIM
Low Impact Development Cleared 9/8/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/8/2021 DINAH GARIN
Hydrant and Access approval Cleared 9/20/2021 ROBERT DUFF
Excavation more than 5-ft deep Cleared 4/6/2022 CALOSHA APPROVED
GPI Written Notices Cleared 4/6/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 4/6/2022 REZA HAGHIGHAT

Contact Information

Contractor Mlr Development Corporation; Lic. No.: 1027283-B 15720 VENTURA BLVD SUITE 405      ENCINO, CA 91436
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/21/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 8/24/2023 No Access for Inspection OGANES TARAKHCHYAN
Deputy Steel/Welding 9/27/2023 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 10/2/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 10/3/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 10/31/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 11/6/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 11/7/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/7/2023 Partial Approval ARAM AVEDISIAN
Deputy Shotcrete 11/13/2023 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/30/2023 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 12/1/2023 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 12/18/2023 Approved ARAM AVEDISIAN
Deputy Reinf. Concrete 12/19/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 1/29/2024 Approved MEL KHACHATOURIAN
Deputy Wood Construction 1/31/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Partial Approval ARAM AVEDISIAN
Deputy Wood Construction 3/26/2024 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Approved ARAM AVEDISIAN
HVAC-Rough 3/28/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 5/15/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/15/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 5/16/2024 Approved ARAM AVEDISIAN
Shower Pan 6/4/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/5/2024 Conditional Approval ARAM AVEDISIAN
Green Building Rough 6/5/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/5/2024 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/5/2024 Approved ARAM AVEDISIAN
Insulation 6/10/2024 Not Ready for Inspection ARAM AVEDISIAN
Insulation 6/13/2024 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 6/13/2024 Not Ready for Inspection STEPHANIE SWANSON
Insulation 6/18/2024 Approved ARAM AVEDISIAN
Drywall Nailing 6/21/2024 Approved ARAM AVEDISIAN
Gas Test 10/4/2024 Approved REGINA MENDEZ
Sewer 10/4/2024 Approved REGINA MENDEZ
Grounding or Bonding 10/30/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Final 2/14/2025 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 4/1/2025 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 5/16/2025 Approved HERBERT GIRON
ELECTRICAL-Final 5/16/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 5/16/2025 Corrections Issued HERBERT GIRON
Reinforced Concrete Frame 5/16/2025 Approved HERBERT GIRON
ELECTRICAL-Final 5/22/2025 Corrections Issued HERBERT GIRON
HVAC-Final 5/31/2025 Corrections Issued BOBBY KEY
PLUMBING-Final 5/31/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/31/2025 SGSOV Approved BOBBY KEY
Smoke Detectors 5/31/2025 Approved BOBBY KEY
Gas Test 6/5/2025 Approved HERBERT GIRON
HVAC-Final 6/5/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/5/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Approved HERBERT GIRON
Final 6/6/2025 Corrections Issued HERBERT GIRON
Green Building Final 6/6/2025 Approved HERBERT GIRON
HVAC-Final 6/6/2025 Approved HERBERT GIRON
Final 6/10/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 7/17/2025 Approved HERBERT GIRON
Final 7/17/2025 OK to Issue CofO HERBERT GIRON
Service/Power Release 7/17/2025 Approved HERBERT GIRON