3663 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3663 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21010-30000-01071
- Plan Check / Job No.
- B21WL00966
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new 2-story garage & ADU
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | TARIK SAOUD |
| Corrections Issued | 4/7/2021 | TARIK SAOUD |
| Quality Review Completed | 4/14/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/3/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/24/2021 | TARIK SAOUD |
| Plan Check Approved | 11/10/2021 | TARIK SAOUD |
| Issued | 12/10/2021 | APPLICANT |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| CofO in Progress | 6/28/2023 | JOHNNY MIRANDA |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
| CofO Issued | 7/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2021 | DINAH GARIN |
| Permit | Cleared | 4/23/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/11/2021 | DINAH GARIN |
| Specific Plan | Cleared | 6/3/2021 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 7/12/2021 | MATTHEW CRAIG |
| Frnt yard landscape/Water mgmt | Cleared | 8/26/2021 | RICHARD REASER |
| Low Impact Development | Cleared | 9/23/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 10/13/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 11/9/2021 | TARIK SAOUD |
Contact Information
| Architect | Rees,, Robert S; Lic. No.: C26934 | 3483 BARRY AVENUE LOS ANGELES, CA 90066 |
| Contractor | Mackey And Son Inc; Lic. No.: 790087-B | 10945 DARBY AVENUE PORTER RANCH, CA 91326 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/15/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Pre-Inspection | 2/15/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/10/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/19/2022 | Partial Approval | EVAN COOPER |
| Sewer | 4/19/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 5/3/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/2/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 12/2/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/2/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/13/2023 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 1/13/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/19/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 1/25/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/25/2023 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/25/2023 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 1/25/2023 | Approved | JOHNNY MIRANDA |
| Wood Frame | 1/25/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 2/15/2023 | Approved | EVAN COOPER |
| Insulation | 2/15/2023 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 2/27/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 5/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 5/25/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 6/1/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 6/1/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 6/1/2023 | Corrections Issued | JOHNNY MIRANDA |
| Service/Power Release | 6/6/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/9/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/9/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 6/9/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 6/9/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/22/2023 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Final | 6/22/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | JOHNNY MIRANDA |