3665 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3665 S MOUNTAIN VIEW AVE 90066

Application / Permit
21010-30000-01070
Plan Check / Job No.
B21WL00966
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Two Story S.F.D
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 TARIK SAOUD
Corrections Issued 4/7/2021 TARIK SAOUD
Quality Review Completed 4/14/2021 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/3/2021 DAVID CASTILLO
Applicant returned to address corrections 8/24/2021 TARIK SAOUD
Plan Check Approved 11/10/2021 TARIK SAOUD
Issued 12/10/2021 APPLICANT
Building Plans Picked Up 12/15/2021 APPLICANT
CofO in Progress 6/28/2023 JOHNNY MIRANDA
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2021 DINAH GARIN
Sewer availability Cleared 5/11/2021 DINAH GARIN
Specific Plan Cleared 6/3/2021 VALERIA CEJA
Hydrant and Access approval Cleared 7/12/2021 MATTHEW CRAIG
Grading Pre-Inspection Cleared 8/3/2021 TARIK SAOUD
Frnt yard landscape/Water mgmt Cleared 8/26/2021 RICHARD REASER
Low Impact Development Cleared 9/23/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 10/8/2021 ANTHONY MAINEZ

Contact Information

Architect Rees,, Robert S; Lic. No.: C26934 3483 BARRY AVENUE      LOS ANGELES, CA 90066
Contractor Mackey And Son Inc; Lic. No.: 790087-B 10945 DARBY AVENUE      PORTER RANCH, CA 91326
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2022 Corrections Issued JOHNNY MIRANDA
Pre-Inspection 2/15/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 3/10/2022 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 3/15/2022 Conditional Approval JOHNNY MIRANDA
PLUMBING-Rough 4/19/2022 Partial Approval EVAN COOPER
Sewer 4/19/2022 Approved EVAN COOPER
Footing/Foundation/Slab 5/3/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 12/2/2022 Corrections Issued CARLOS MATAMOROS
Gas Test 12/2/2022 Approved CARLOS MATAMOROS
HVAC-Rough 12/2/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 12/2/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/9/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 12/9/2022 Approved JOHNNY MIRANDA
Green Building Rough 12/9/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 12/9/2022 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 12/9/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 12/15/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 12/15/2022 Approved JOHNNY MIRANDA
Underground Mechanical 12/19/2022 Partial Approval KENNETH NAGLE
Insulation 12/23/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 1/13/2023 Approved JOHNNY MIRANDA
Insulation 1/13/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 1/13/2023 Partial Approval JOHNNY MIRANDA
Shower Pan 1/13/2023 Approved JOHNNY MIRANDA
Drywall Nailing 1/19/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 1/19/2023 Partial Approval JOHNNY MIRANDA
Gas Test 5/5/2023 Approved JOHNNY MIRANDA
PLUMBING-Final 5/5/2023 Not Ready for Inspection JOHNNY MIRANDA
Underground Mechanical 5/5/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Final 5/24/2023 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 5/25/2023 Approved JOHNNY MIRANDA
Pre-Inspection 5/30/2023 Approved JOHNNY MIRANDA
HVAC-Final 6/1/2023 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Final 6/1/2023 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 6/9/2023 Approved JOHNNY MIRANDA
Final 6/9/2023 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 6/9/2023 Approved JOHNNY MIRANDA
Green Building Final 6/9/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Final 6/9/2023 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 6/9/2023 Approved JOHNNY MIRANDA
Smoke Detectors 6/9/2023 Approved JOHNNY MIRANDA
Final 6/22/2023 Conditional Approval JOHNNY MIRANDA
Green Building Final 6/22/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Approved JOHNNY MIRANDA