14928 W LA CUMBRE DR 90272
Certificate Information: 14928 W LA CUMBRE DR 90272
- Application / Permit
- 21010-30000-00981
- Plan Check / Job No.
- B21WL00911
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD WITH BASEMENT AND ATTACHED GARAGE.
- Permit Issued
- Issued on 8/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2021 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 3/29/2021 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 3/31/2021 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 5/25/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/27/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 8/12/2021 | ALFREDO JARA |
| Plan Check Approved | 8/25/2021 | ALFREDO JARA |
| Issued | 8/27/2021 | APPLICANT |
| No Progress | 2/29/2024 | KENNETH NAGLE |
| CofO in Progress | 2/29/2024 | KENNETH NAGLE |
| CofO in Progress | 2/29/2024 | EVAN COOPER |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
| CofO Issued | 3/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 4/13/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/14/2021 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 4/29/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 5/14/2021 | MATTHEW CRAIG |
| Excavation more than 5-ft deep | Cleared | 5/26/2021 | CALOSHA APPROVED |
| Coastal Zone | Cleared | 6/8/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 6/22/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/23/2021 | DENNIS BRAGIN |
| Zoning Information File | Cleared | 7/22/2021 | KAMRAN GHOTBI RAVANDI |
Contact Information
| Contractor | Shore Real Estate Development; Lic. No.: 914609-B | 270 N CANON DRIVE 3RD FLOOR BEVERLY HILLS, CA 90210 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/20/2021 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 11/18/2021 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 11/23/2021 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 1/10/2022 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 1/11/2022 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 1/21/2022 | Corrections Issued | JOHN KIDWELL |
| Underground Mechanical | 1/24/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 2/3/2022 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 2/22/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/12/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/13/2022 | Approved | JOHN KIDWELL |
| Deputy Steel/Welding | 5/26/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 6/29/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Corrections Issued | ANDREW NAVE |
| Wood Frame | 9/22/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 10/27/2022 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 11/1/2022 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 11/1/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 11/2/2022 | Partial Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 11/17/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 11/21/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 11/29/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/30/2022 | Partial Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/7/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/9/2022 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/13/2022 | Conditional Approval | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 12/13/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 12/14/2022 | Approved | BRENDAN LOONEY |
| Insulation | 12/19/2022 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 12/20/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Shower Pan | 12/23/2022 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 1/4/2023 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 1/10/2023 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 1/19/2023 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 1/23/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 6/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 6/1/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/13/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/15/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/29/2023 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/11/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 12/14/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/20/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/27/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 1/3/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/27/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 2/27/2024 | Approved | EVAN COOPER |
| Final | 2/27/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 2/27/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 2/27/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 2/27/2024 | Approved | EVAN COOPER |
| Final | 2/28/2024 | Conditional Approval | EVAN COOPER |
| Final | 2/29/2024 | OK to Issue CofO | EVAN COOPER |