813-815 N ORANGE DR 90038
Certificate Information: 813-815 N ORANGE DR 90038
- Application / Permit
- 21010-30000-00954
- Plan Check / Job No.
- B21WL00882
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (n) 2-family dwelling. both with 2-car garage and roof trusses
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- CofO Issued on 1/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 3/25/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 3/31/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 6/11/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/23/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 8/24/2021 | APPLICANT |
| Plan Check Approved | 8/30/2021 | FELIPE HERNANDEZ |
| Issued | 9/3/2021 | APPLICANT |
| CofO in Progress | 1/19/2023 | MICHAEL LEWIS |
| CofO in Progress | 1/19/2023 | MICHAEL LEWIS |
| CofO in Progress | 1/20/2023 | MICHAEL LEWIS |
| Permit Finaled | 1/26/2023 | DEROLD HAUFF |
| CofO Issued | 1/26/2023 | DEROLD HAUFF |
| Permit Finaled | 1/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2021 | WALLIE JONG |
| Permit | Cleared | 6/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 8/3/2021 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 8/4/2021 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 8/9/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/10/2021 | WALLIE JONG |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/29/2021 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 10/13/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Approved | CRAIG DAVIS |
| Deputy Wood Construction | 10/29/2021 | Conditional Approval | ROBERT CORNELL |
| Excavation/Setback/Form/Re-Bar | 10/29/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 11/10/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 12/1/2021 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 12/9/2021 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 12/22/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/22/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/6/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/6/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 1/14/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 2/2/2022 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 2/4/2022 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/10/2022 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/10/2022 | Partial Approval | BRIAN SULLIVAN |
| METHANE-Rough | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 4/8/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 4/19/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/19/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 7/1/2022 | Conditional Approval | RAUL BARAJAS |
| HVAC-Final | 7/1/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 7/1/2022 | Conditional Approval | RAUL BARAJAS |
| ELECTRICAL-Final | 10/19/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 10/19/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 10/19/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/24/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | BRIAN SULLIVAN |
| Final | 11/21/2022 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 11/21/2022 | Approved | BRIAN SULLIVAN |
| Green Building Final | 11/21/2022 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 11/21/2022 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 11/21/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 11/21/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 11/21/2022 | Approved | BRIAN SULLIVAN |
| Final | 12/30/2022 | Corrections Issued | RAUL BARAJAS |
| Final | 1/9/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Service/Power Release | 1/9/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 1/11/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 1/13/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 1/18/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Final | 1/19/2023 | OK to Issue CofO | MICHAEL LEWIS |