813-815 N ORANGE DR 90038

Certificate Information: 813-815 N ORANGE DR 90038

Application / Permit
21010-30000-00954
Plan Check / Job No.
B21WL00882
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(n) 2-family dwelling. both with 2-car garage and roof trusses
Permit Issued
Issued on 9/3/2021
Issuing Office
Current Status
CofO Issued on 1/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 FELIPE HERNANDEZ
Corrections Issued 3/25/2021 FELIPE HERNANDEZ
Quality Review Completed 3/31/2021 TARIK SAOUD
Applicant returned to address corrections 6/11/2021 FELIPE HERNANDEZ
Applicant returned to address corrections 8/23/2021 FELIPE HERNANDEZ
Building Plans Picked Up 8/24/2021 APPLICANT
Plan Check Approved 8/30/2021 FELIPE HERNANDEZ
Issued 9/3/2021 APPLICANT
CofO in Progress 1/19/2023 MICHAEL LEWIS
CofO in Progress 1/19/2023 MICHAEL LEWIS
CofO in Progress 1/20/2023 MICHAEL LEWIS
Permit Finaled 1/26/2023 DEROLD HAUFF
CofO Issued 1/26/2023 DEROLD HAUFF
Permit Finaled 1/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/10/2021 WALLIE JONG
Permit Cleared 6/10/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/14/2021 WALLIE JONG
Low Impact Development Cleared 8/3/2021 SARAH YOUSSEF
Hydrant and Access approval Cleared 8/4/2021 KURT CORRAL
Roof/Waste drainage to street Cleared 8/9/2021 WALLIE JONG
Sewer availability Cleared 8/10/2021 WALLIE JONG

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Arriola,, Kirby Norman; Lic. No.: C31416 PO BOX 5566      OXNARD, CA 93031
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/29/2021 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 10/13/2021 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/15/2021 Approved CRAIG DAVIS
Deputy Wood Construction 10/29/2021 Conditional Approval ROBERT CORNELL
Excavation/Setback/Form/Re-Bar 10/29/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval JOSEPH MCGARRY
Underground Mechanical 11/10/2021 Partial Approval SCOTT FINNILA
Deputy Wood Construction 12/1/2021 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 12/9/2021 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 12/22/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 12/22/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 1/6/2022 Approved JOSE AVILA
PLUMBING-Rough 1/6/2022 Corrections Issued JOSE AVILA
HVAC-Rough 1/14/2022 Approved RAUL BARAJAS
Shower Pan 2/2/2022 Approved BRIAN SULLIVAN
Deputy Wood Construction 2/4/2022 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/10/2022 Corrections Issued BRIAN SULLIVAN
Green Building Rough 3/10/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/10/2022 Partial Approval BRIAN SULLIVAN
METHANE-Rough 3/10/2022 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 3/10/2022 Approved BRIAN SULLIVAN
Insulation 4/8/2022 Approved BRIAN SULLIVAN
Drywall Nailing 4/19/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 4/19/2022 Approved ADAM ESCOTO
ELECTRICAL-Final 7/1/2022 Conditional Approval RAUL BARAJAS
HVAC-Final 7/1/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 7/1/2022 Conditional Approval RAUL BARAJAS
ELECTRICAL-Final 10/19/2022 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 10/19/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 10/19/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 10/24/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/21/2022 Approved BRIAN SULLIVAN
Final 11/21/2022 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 11/21/2022 Approved BRIAN SULLIVAN
Green Building Final 11/21/2022 Approved BRIAN SULLIVAN
METHANE-Barrier 11/21/2022 Approved BRIAN SULLIVAN
METHANE-Subgrade 11/21/2022 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 11/21/2022 Approved BRIAN SULLIVAN
Smoke Detectors 11/21/2022 Approved BRIAN SULLIVAN
Final 12/30/2022 Corrections Issued RAUL BARAJAS
Final 1/9/2023 Corrections Issued JOAQUIN GREENOUGH
Service/Power Release 1/9/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 1/11/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 1/13/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 1/18/2023 Partial Approval JOAQUIN GREENOUGH
Final 1/19/2023 OK to Issue CofO MICHAEL LEWIS